RSK-0033Government Fibre Backbone — Damascus–Homs Segment
City councils objecting to digging in built-up neighbourhoods
A risk's detail, response, contingency and residual risk.
Risk statement
From cause to event to impact — with the preventive controls before the event and the contingency after it
Cause
Weak engagement of the owning ministries, governorate councils and beneficiaries, and diverging expectations
Preventive controls
- An updated engagement and communication plan
- Regular meetings with the parties concerned
2 / 2
Event
City councils objecting to digging in built-up neighbourhoods
A formal objection from a stakeholder
Contingency
Take it to the national steering committee
Impact
Objections, late approvals and low adoption
Assessment
The level before and after the response
Inherent
Residual
Exposure
SYP 55M
Residual
67% off the score
Score trend
Last six months
- Score
- Target residual
Escalation path
Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the PMO director
Last reviewed 37 days ago · Outside the engine — below «high»
Project manager
Current levelEng. George Haddad
Currently followed up here- 2
Programme manager
Eng. George Haddad
- 3
PMO director
Dr. Reem Al-Qabbani
- 4
Executive Council
Dr. Samer Al-Daqqar
By the PMO director’s decision
Mitigation plan
Each action with its owner and date — tick it off when complete
An updated engagement and communication plan
Eng. George HaddadEng. George HaddadDirector, Data Centres & Government NetworkP-024george.haddad@psa.gov.syIn progressIn 33 days2026-11-30Regular meetings with the parties concerned
Eng. George HaddadEng. George HaddadDirector, Data Centres & Government NetworkP-024george.haddad@psa.gov.syNot startedIn 33 days2026-11-30
Trigger
A formal objection from a stakeholder
Contingency
Take it to the national steering committee