Internal
Syrian Arab Republic
Planning and Statistics Authority
National Project Management Office (PMO)
- Code
- DOC-0215
- Version
- V2
- Date
- 2026-10-18
Geotechnical report, axes 12–16 — Douma plant
Douma Wastewater Treatment Plant
1. Executive summary
This report gives the position of Douma Wastewater Treatment Plant to date: 44% complete against 55% planned, SPI 0.80, CPI 0.95, and an estimate at completion of SYP 9.08bn.
- Project
- Douma Wastewater Treatment Plant (PRJ-2026-020)
- Project manager
- Eng. Qasem Al-Hariri
- Budget
- SYP 8.63bn
- Progress
- 44% actual against 55% planned
- Forecast finish
- 2027-08-03
2. Key findings
- All planned milestones of the period met except one deferred
- Actual spend rose in line with the work done
- Three high risks under treatment, each with a named owner
3. Recommendations & decisions needed
- Approve the proposed treatment of the high risks
- Track the open findings with the vendor weekly
Prepared by
Eng. Qasem Al-Hariri
Internal