Geotechnical report, axes 12–16 — Douma plant

InternalReturnedV2

⁦Geotechnical report for axes 12 to 16 on the Douma wastewater treatment plant site⁩, with foundation and groundwater recommendations.

More
Showing version:

Internal

Syrian Arab Republic

Planning and Statistics Authority

National Project Management Office (PMO)

Code
DOC-0215
Version
V2
Date
2026-10-18

Geotechnical report, ⁦axes 12⁩–⁦16⁩ — Douma plant

Douma Wastewater Treatment Plant

⁦1⁩. Executive summary

This report gives the position of Douma Wastewater Treatment Plant to date: ⁦44% complete against 55% planned⁩, ⁦SPI 0⁩.⁦80⁩, ⁦CPI 0⁩.⁦95⁩, ⁦and an estimate at completion of SYP 9⁩.⁦08bn⁩.

Project
Douma Wastewater Treatment Plant (⁦PRJ-2026-020⁩)
Project manager
Eng. Qasem Al-Hariri
Budget
⁦SYP 8⁩.⁦63bn⁩
Progress
⁦44% actual against 55% planned⁩
Forecast finish
⁦2027-08-03⁩

⁦2⁩. Key findings

  • All planned milestones of the period met except one deferred
  • Actual spend rose in line with the work done
  • Three high risks under treatment, each with a named owner

⁦3⁩. Recommendations & decisions needed

  • Approve the proposed treatment of the high risks
  • Track the open findings with the vendor weekly

Prepared by

Eng. Qasem Al-Hariri
Issued from Munjaz — valid only once approved electronically1 / 1