CP-2026-04Version 1
Douma Wastewater Treatment Plant
One corrective plan: why the project slipped, the rule that triggered it, the actions, the days won back, approval and follow-up.
What triggered the plan
The project’s reading the day the rule fired, and today.
Detected on 2026-08-04
Slip past the baseline
- At detection
- 55 days
- Today
- 64 days
- Limit
- > 40
Schedule performance index
- At detection
- 0.83
- Today
- 0.80
- Limit
- < 0.85
A rule approved by the Project Approval Committee (PMO-2026/14), read automatically from the project’s data.
Days won back
The forecast finish without the plan, with it, and the difference.
Baseline
2027-05-31Without the plan
2027-09-05+97 days
With the plan
2027-08-03+64 days
Wins back 33 days
Achieved so far: 0 days
Why it slipped
Clay layers, voids and groundwater under the foundations of axes 12 to 16 that the initial soil tests missed
Corrective actions
Each action with its owner, date, status and the days it wins back; overdue ones are shaded.
Extra soil tests at axes 12 to 16
Eng. Qasem Al-HaririEng. Qasem Al-HaririDirector, Transport & Housing ProjectsP-020qasem.alhariri@psa.gov.syDone2026-10-202026-10-20Redesign the foundations through a change request
Eng. Qasem Al-HaririEng. Qasem Al-HaririDirector, Transport & Housing ProjectsP-020qasem.alhariri@psa.gov.syCR-2026-010In progressIn 7 days2026-11-04Wins back 10 daysDewatering at axis 14
Eng. Adnan Al-MohammadEng. Adnan Al-MohammadSenior Site Engineer (Contractor)P-043adnan.almohammad@psa.gov.syIn progressIn 11 days2026-11-08Wins back 8 daysApprove the geotechnical report for axes 12–16
Eng. Qasem Al-HaririEng. Qasem Al-HaririDirector, Transport & Housing ProjectsP-020qasem.alhariri@psa.gov.syACT-0320In progressIn 11 days2026-11-08A second shift casting the treatment basins once the foundations are done
Eng. Qasem Al-HaririEng. Qasem Al-HaririDirector, Transport & Housing ProjectsP-020qasem.alhariri@psa.gov.syNot startedIn 34 days2026-12-01Wins back 15 days
Follow-up
The project’s readings after the plan was approved, with the PMO’s notes.
2026-10-27Kinan Azzam64 days lateSPI 0.80
Groundwater stopped excavation at axis 14 (ISS-0123); no days won back yet
2026-09-29Kinan Azzam60 days lateSPI 0.81
Extra soil tests complete; the redesign request is filed