PRJ-2026-020Off track4ExecutionConstructionStalledDelivered by:Ministry of Local Administration and Environment

Douma Wastewater Treatment Plant

Remove from watchlist

A wastewater treatment plant in Douma serving the city and nearby towns, financed by the Syrian Development Fund, with the main trunk lines and treated water reused for irrigation.

Early warning: ⁦81%⁩ chance of slipping within ⁦60⁩ days

Budget (BAC)

SYP 8.6B

Actual cost

SYP 4B

⁦46%⁩ of budget

Progress

⁦44%⁩Awaiting acceptance ⁦12%⁩

Estimate at completion

SYP 9.1B

+SYP 453.9M

SPI · CPI

0.80Schedule performance index · 0.800.95Cost performance index · 0.95

Forecast finish

⁦2027-08-03⁩

64 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure5 March 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 April 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate2 June 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate24 November 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate5 March 2027Closure · Not startedClosure · Not started

Corrective plan

Actions, owners, dates and status

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Corrective plan

Actions, owners, dates and status

Form no.
PSA-PMO-F11
Template edition
1.4
Version
V1
Form date
⁦2026-08-18⁩
ApprovedCP-2026-04Corrective plan — Douma Wastewater Treatment Plant

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-020
Project
Douma Wastewater Treatment Plant
Portfolio
Reconstruction & Infrastructure Portfolio
Sector
Development Projects Follow-up Sector
Sponsor
Salma Al-Zaim
Project manager
Eng. Qasem Al-Hariri

1Why the planAuto-filled

Slip when detected

55 days

SPI

0.83

Finish without the plan

⁦2027-09-05⁩

Finish with the plan

⁦2027-08-03⁩

Causes

Clay layers, voids and groundwater under the foundations of axes 12 to 16 that the initial soil tests missed

2Actions

ActionOwnerDueStatusDays won back
Extra soil tests at axes 12 to 16Eng. Qasem Al-Hariri⁦2026-10-20⁩Done0
Redesign the foundations through a change requestEng. Qasem Al-Hariri⁦2026-11-04⁩In progress10
Dewatering at axis 14Eng. Adnan Al-Mohammad⁦2026-11-08⁩In progress8
Approve the geotechnical report for axes 12–16Eng. Qasem Al-Hariri⁦2026-11-08⁩In progress0
A second shift casting the treatment basins once the foundations are doneEng. Qasem Al-Hariri⁦2026-12-01⁩Not started15
Total———33

3PMO follow-upAuto-filled

DateSPISlipNote
⁦2026-10-27⁩0.8064Groundwater stopped excavation at axis 14 (ISS-0123); no days won back yet
⁦2026-09-29⁩0.8160Extra soil tests complete; the redesign request is filed

Approval logChain: Corrective plan approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Qasem Al-HaririDirector, Transport & Housing ProjectsSubmitted—⁦2026-08-18⁩ 13:10
2Programme manager reviewTechnical acceptanceDr. Reem Al-QabbaniProgramme managerApproved—⁦2026-08-19⁩ 09:42
3National Projects Steering Committee approvalTechnical acceptanceDr. Samer Al-DaqqarNational Projects Steering CommitteeApproved—⁦2026-08-26⁩ 11:56

Signatures

Programme manager review

Dr. Reem Al-Qabbani

Approved⁦2026-08-19⁩

National Projects Steering Committee approval

Dr. Samer Al-Daqqar

Approved⁦2026-08-26⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F11 · version V1

Corrective plan

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Corrective plan approval · version ⁦1⁩

Submitted by Eng. Qasem Al-Hariri on ⁦2026-08-18⁩

  1. Technical acceptance

    Programme manager review

    Dr. Reem Al-Qabbani · Programme manager

    Approved · ⁦2026-08-19⁩ at ⁦09:42⁩

  2. Technical acceptance

    National Projects Steering Committee approval

    Dr. Samer Al-Daqqar · National Projects Steering Committee

    Approved · ⁦2026-08-26⁩ at ⁦11:56⁩

Steps that do not apply to this record

  • Financial support requested — the condition «Financial link?» does not hold

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V1ApprovedCurrent⁦2026-08-18⁩

    The current version

    Eng. Qasem Al-Hariri

Only one version so far.