PRJ-2026-009At risk4ExecutionHybridIn progressDelivered by:Ministry of Communications and Information Technology

Government Cloud & Ministry Systems Migration

Add to watchlist

Building the government cloud in the government data centre and moving the ministries’ systems and websites onto it in waves, retiring scattered servers.

Budget (BAC)

SYP 1.3B

Actual cost

SYP 629.9M

⁦48%⁩ of budget

Progress

⁦47%⁩Awaiting acceptance ⁦12%⁩

Estimate at completion

SYP 1.3B

+SYP 40.2M

SPI · CPI

0.89Schedule performance index · 0.890.97Cost performance index · 0.97

Forecast finish

⁦2027-03-21⁩

21 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure8 January 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate2 April 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate1 June 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate11 September 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate8 January 2027Closure · Not startedClosure · Not started

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

−8

May to October 2026

No material change in the health dimensions over the period.

Copilot summary

Generated from the live project data

The project is behind plan: ⁦47% done against 53% planned⁩.

⁦SPI 0⁩.⁦89⁩, ⁦CPI 0⁩.⁦97⁩.

The project’s link, progress and status

How the project ties to the strategy, its progress counted from accepted deliverables, and its status history.

Strategic link

The main objective and initiative, the secondary links, and the project’s contribution to its initiative.

Main strategic objective· Axis: Governance & Digital TransformationSO-5.2Sound governance and effective follow-up of projects and data

Main initiative

SI-5.2.1Government cloud & cybersecurity

Contribution to the initiative⁦22%⁩

The project’s share of the initiative’s project budget (3 projects)

Secondary links

No secondary links

Annual work-plan line
WP-2025-009
Classification
Operational

Project progress from accepted deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate; nothing counts before acceptance.

Counted

⁦47%⁩

Awaiting acceptance ⁦12%⁩

Not handed in ⁦41%⁩

5 deliverables accepted

  • Release 1⁦16%⁩
  • Business requirements⁦11%⁩
  • Solution design⁦10%⁩
  • Project plan & baseline⁦5%⁩
  • Monitoring & reporting⁦5%⁩

1 deliverable under inspection or acceptance

  • Release 2⁦12%⁩

Progress & earned value

⁦3⁩ of ⁦5⁩ milestones complete

Earned-value curve

Planned, earned and actual to the data date, cumulative, with the forecast cost tail

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Budget & commitments

Commitments are ⁦79%⁩ of budget

SYP629.9M/ SYP1.3BSYP40.2Mprojected overrun(⁦3.1%⁩)
Actual spend
SYP629.9M
Committed
SYP1B
Approved budget
SYP1.3B
Estimate at completion
SYP1.3B

Next milestones

  • Provisional acceptance⁦2027-01-24⁩was ⁦2027-01-08⁩At risk
  • Closure⁦2027-03-21⁩was ⁦2027-02-28⁩Late

Waiting on someone

⁦0⁩ approvals and ⁦0⁩ open actions on this project

Approvals & requests

From «My actions» for this project

  • No approvals pending

Actions

⁦0⁩ open

  • No actions on this project

Change requests

Cost and schedule impact

  • No change requests

Risks & impediments

1 open risk, exposure SYP 65M

Risk map

Probability
5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩Probability: Almost certain · Impact: SevereCritical · Score ⁦25⁩
4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩Probability: Likely · Impact: MajorHigh · Score ⁦16⁩Probability: Likely · Impact: SevereCritical · Score ⁦20⁩
3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩1Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩RSK-0029Government cloud resource cost above estimateProbability: Possible · Impact: MajorMedium · Score ⁦12⁩Probability: Possible · Impact: SevereHigh · Score ⁦15⁩
2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩Probability: Unlikely · Impact: SevereMedium · Score ⁦10⁩
1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
12345

Impact

  • Critical0
  • High0
  • Medium1
  • Low0

Open impediments

⁦0⁩ escalated

  • No open impediments

Deliverables

⁦5⁩ of ⁦11⁩ approved

  • Project plan & baseline009-D1 · V1 · CRT-009-01⁦5%⁩Eng. George Haddad2025-08-282025-08-28Approved
  • Monitoring & reporting009-D2 · V1 · CRT-009-02⁦5%⁩Eng. Mazen Kassab2025-10-222025-10-22Approved
  • Business requirements009-D3 · V1 · CRT-009-03⁦11%⁩Eng. Mazen Kassab2025-12-162025-12-16Approved
  • Solution design009-D4 · V1 · CRT-009-04⁦10%⁩Eng. Khaled Al-Kayyali2026-02-092026-02-09Approved
  • Release 1009-D5 · V1 · CRT-009-05⁦16%⁩Eng. Khaled Al-Kayyali2026-04-052026-04-05Approved
  • Release 2009-D6 · V1⁦12%⁩Eng. George Haddad152 days overdue2026-05-29In review
  • Integrations009-D7 · V0⁦11%⁩Eng. Mazen Kassab97 days overdue2026-07-23Draft
  • System testing009-D8 · V0⁦9%⁩Eng. George Haddad42 days overdue2026-09-16Draft
  • User acceptance testing009-D9 · V0⁦9%⁩Eng. Mazen KassabIn 13 days2026-11-10Draft
  • Training & change009-D10 · V0⁦6%⁩Eng. Mazen KassabIn 68 days2027-01-04Draft
  • Go-live & handover009-D11 · V0⁦6%⁩Eng. Khaled Al-KayyaliIn 123 days2027-02-28Draft

Team, contracts & documents

Team

3 members

Eng. George Haddad · Director, Data Centres & Government NetworkEng. Mazen Kassab · Director General, Government Digital InfrastructureEng. Saleh Al-Bakir · Cloud & Integration Engineer
  • Eng. George HaddadEng. George HaddadDirector, Data Centres & Government NetworkProject managerP-024george.haddad@psa.gov.sy⁦40%⁩
  • Eng. Mazen KassabEng. Mazen KassabDirector General, Government Digital InfrastructureProject ownerP-017mazen.kassab@psa.gov.sy⁦20%⁩
  • Eng. Saleh Al-BakirEng. Saleh Al-BakirCloud & Integration EngineerMinistry systems migration to the government cloudP-034saleh.albakir@psa.gov.sy⁦30%⁩