PRJ-2026-009At risk4ExecutionHybridIn progressDelivered by:Ministry of Communications and Information Technology

Government Cloud & Ministry Systems Migration

Add to watchlist

Building the government cloud in the government data centre and moving the ministries’ systems and websites onto it in waves, retiring scattered servers.

Budget (BAC)

SYP 1.3B

Actual cost

SYP 629.9M

⁦48%⁩ of budget

Progress

⁦47%⁩Awaiting acceptance ⁦12%⁩

Estimate at completion

SYP 1.3B

+SYP 40.2M

SPI · CPI

0.89Schedule performance index · 0.890.97Cost performance index · 0.97

Forecast finish

⁦2027-03-21⁩

21 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure8 January 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate2 April 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate1 June 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate11 September 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate8 January 2027Closure · Not startedClosure · Not started

Baselines

The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.

  1. Original

    Original baseline

    v1.0Approved & lockedVersion A
    Finish
    ⁦2027-02-28⁩
    Budget
    SYP 1.3B
    ⁦16⁩ activities

    Approved with the project plan at the planning gate.

    Approved ⁦2025-06-01⁩ · by Eng. Khaled Al-Kayyali

  2. Working

    Working baseline

    v2.0-draftWorking draftVersion B
    Finish
    ⁦2027-03-18⁩
    ⁦+18⁩ days
    Budget
    SYP 1.3B
    ⁦16⁩ activities

    Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.

    Created ⁦2026-10-28⁩ · by Eng. George Haddad

    Edit in the schedule

Compare two versions

What changed from version A to version B

Finish

⁦2027-02-28⁩⁦2027-03-18⁩

⁦+18⁩ days

Budget

SYP 1.3BSYP 1.3B

⁦0.00⁩ SYP M

Milestones moved

5 / 5

Milestones: A to B

Each line starts at the milestone’s date in A and ends at its date in B

2026-012026-072027-01
  • Project plan approved⁦+95⁩
  • Designs approved⁦+169⁩
  • Build complete⁦+150⁩
  • Testing & acceptance complete⁦+84⁩
  • Final handover⁦+18⁩

Version AVersion B

Cost by WBS element

Difference in SYP millions from A to B

  • 1Management & governance⁦+6.34⁩
  • 2Analysis & design⁦+13.47⁩
  • 3Build⁦+38.85⁩
  • 4Testing & acceptance⁦+15.46⁩
  • 5Launch & handover⁦+11.60⁩

Version history

Every saved version with its reason and reference

  1. Working baselinev2.0-draftWorking draftFollows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.⁦2026-10-28⁩by Eng. George Haddad
  2. Original baselinev1.0Approved & lockedApproved with the project plan at the planning gate.⁦2025-06-01⁩by Eng. Khaled Al-Kayyali