Original
Original baseline
- Finish
- 2027-02-28
- Budget
- SYP 1.3B
- 16 activities
Approved with the project plan at the planning gate.
Approved 2025-06-01 · by Eng. Khaled Al-Kayyali
Building the government cloud in the government data centre and moving the ministries’ systems and websites onto it in waves, retiring scattered servers.
Budget (BAC)
Actual cost
48% of budget
Progress
Estimate at completion
+SYP 40.2M
SPI · CPI
Forecast finish
21 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure8 January 2027
The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.
Original
Approved with the project plan at the planning gate.
Approved 2025-06-01 · by Eng. Khaled Al-Kayyali
Working
Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.
Created 2026-10-28 · by Eng. George Haddad
What changed from version A to version B
Finish
2027-02-282027-03-18
+18 days
Budget
SYP 1.3BSYP 1.3B
0.00 SYP M
Milestones moved
5 / 5
Each line starts at the milestone’s date in A and ends at its date in B
Version AVersion B
Difference in SYP millions from A to B
Every saved version with its reason and reference