PRJ-2026-009At risk4ExecutionHybridIn progressDelivered by:Ministry of Communications and Information Technology
Government Cloud & Ministry Systems Migration
Add to watchlistBuilding the government cloud in the government data centre and moving the ministries’ systems and websites onto it in waves, retiring scattered servers.
Project managerEng. George HaddadProject sponsorEng. Khaled Al-KayyaliProgrammeDigital Infrastructure & Cybersecurity Programme
Budget (BAC)
SYP 1.3B
Actual cost
SYP 629.9M
48% of budget
Progress
47%Awaiting acceptance 12%
Estimate at completion
SYP 1.3B
+SYP 40.2M
SPI · CPI
0.89Schedule performance index · 0.890.97Cost performance index · 0.97
Forecast finish
2027-03-21
21 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure8 January 2027
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate2 April 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionConditional goDate1 June 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate11 September 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate8 January 2027Closure · Not startedClosure · Not started