Government Cloud & Ministry Systems Migration
Add to watchlistBuilding the government cloud in the government data centre and moving the ministries’ systems and websites onto it in waves, retiring scattered servers.
Budget (BAC)
Actual cost
48% of budget
Progress
Estimate at completion
+SYP 40.2M
SPI · CPI
Forecast finish
21 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure8 January 2027
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate2 April 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionConditional goDate1 June 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate11 September 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate8 January 2027Closure · Not startedClosure · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2025-10-22 | 2026-01-25 | +95 days | Eng. George HaddadEng. George HaddadDirector, Data Centres & Government NetworkP-024george.haddad@psa.gov.sy | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2026-02-09 | 2026-07-28 | +169 days | Eng. George HaddadEng. George HaddadDirector, Data Centres & Government NetworkP-024george.haddad@psa.gov.sy | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2026-07-23 | 2026-12-20 | +150 days | Eng. George HaddadEng. George HaddadDirector, Data Centres & Government NetworkP-024george.haddad@psa.gov.sy | Late | 0 | Not requested |
| Testing & acceptance completeMS-G4 | Regulatory | 2026-11-10 | 2027-02-02 | +84 days | Eng. George HaddadEng. George HaddadDirector, Data Centres & Government NetworkP-024george.haddad@psa.gov.sy | At risk | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2027-02-28 | 2027-03-18 | +18 days | Eng. George HaddadEng. George HaddadDirector, Data Centres & Government NetworkP-024george.haddad@psa.gov.sy | On track | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
47%Awaiting acceptance
12%Not handed in
41%Deliverable flow
Display options
| Project plan & baseline009-D1 | 5% | CRT-009-01 | Approved | Eng. George HaddadEng. George HaddadDirector, Data Centres & Government NetworkP-024george.haddad@psa.gov.sy | Eng. Mazen Kassab | 2025-08-28 | V1 | 3 of 3 |
| Monitoring & reporting009-D2 | 5% | CRT-009-02 | Approved | Eng. Mazen KassabEng. Mazen KassabDirector General, Government Digital InfrastructureP-017mazen.kassab@psa.gov.sy | Eng. Mazen Kassab | 2025-10-22 | V1 | 3 of 3 |
| Business requirements009-D3 | 11% | CRT-009-03 | Approved | Eng. Mazen KassabEng. Mazen KassabDirector General, Government Digital InfrastructureP-017mazen.kassab@psa.gov.sy | Eng. Mazen Kassab | 2025-12-16 | V1 | 3 of 3 |
| Solution design009-D4 | 10% | CRT-009-04 | Approved | Eng. Khaled Al-KayyaliEng. Khaled Al-KayyaliDeputy President, Digital TransformationP-011khaled.alkayyali@psa.gov.sy | Eng. Mazen Kassab | 2026-02-09 | V1 | 3 of 3 |
| Release 1009-D5 | 16% | CRT-009-05 | Approved | Eng. Khaled Al-KayyaliEng. Khaled Al-KayyaliDeputy President, Digital TransformationP-011khaled.alkayyali@psa.gov.sy | Eng. Mazen Kassab | 2026-04-05 | V1 | 3 of 3 |
| Release 2009-D6 | 12% | — | Under review | Eng. George HaddadEng. George HaddadDirector, Data Centres & Government NetworkP-024george.haddad@psa.gov.sy | Eng. Mazen Kassab | 2026-05-29 | V1 | 1 of 3 |
| Integrations009-D7 | 11% | — | Draft | Eng. Mazen KassabEng. Mazen KassabDirector General, Government Digital InfrastructureP-017mazen.kassab@psa.gov.sy | Eng. Mazen Kassab | 2026-07-23 | V0 | 0 of 3 |
| System testing009-D8 | 9% | — | Draft | Eng. George HaddadEng. George HaddadDirector, Data Centres & Government NetworkP-024george.haddad@psa.gov.sy | Eng. Mazen Kassab | 2026-09-16 | V0 | 0 of 3 |
| User acceptance testing009-D9 | 9% | — | Draft | Eng. Mazen KassabEng. Mazen KassabDirector General, Government Digital InfrastructureP-017mazen.kassab@psa.gov.sy | Eng. Mazen Kassab | 2026-11-10 | V0 | 0 of 3 |
| Training & change009-D10 | 6% | — | Draft | Eng. Mazen KassabEng. Mazen KassabDirector General, Government Digital InfrastructureP-017mazen.kassab@psa.gov.sy | Eng. Mazen Kassab | 2027-01-04 | V0 | 0 of 3 |
| Go-live & handover009-D11 | 6% | — | Draft | Eng. Khaled Al-KayyaliEng. Khaled Al-KayyaliDeputy President, Digital TransformationP-011khaled.alkayyali@psa.gov.sy | Eng. Mazen Kassab | 2027-02-28 | V0 | 0 of 3 |
| Total · 11 | 100% |