Government Cloud & Ministry Systems Migration
Add to watchlistBuilding the government cloud in the government data centre and moving the ministries’ systems and websites onto it in waves, retiring scattered servers.
Budget (BAC)
Actual cost
48% of budget
Progress
Estimate at completion
+SYP 40.2M
SPI · CPI
Forecast finish
21 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure8 January 2027
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate2 April 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionConditional goDate1 June 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate11 September 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate8 January 2027Closure · Not startedClosure · Not started
Project lifecycle and its gates
Current phase: Execution. Pick a gate on the track to review it.
- Gate into «Initiation»DecisionGoDate2 April 2025All criteria and required documents met.Pre-startComplete
- Gate into «Planning»DecisionConditional goDate1 June 2025Mandatory criteria met, with points to close during the next phase.InitiationComplete
- Gate into «Execution»DecisionGoDate11 September 2025All criteria and required documents met.PlanningComplete
- Gate into «Closure»DecisionNot held yetDate8 January 2027ExecutionCurrent stageCurrent stage
- 5ClosureNot started
What each stage requires
The documents and approvals each gate asks for before the next stage.
Closure gate — deliverables accepted and handed over
Gate readiness
Enough for a conditional go only
Automated control: no move until the criteria are met
- 3 mandatory checklist items open
- 2 required documents not approved
- 1 mandatory criterion under 70 points
- Weighted score 68 under the pass mark 75
Checklist
4 of 7 done
- Deliverable completion certificates approved for every deliverableMandatory
- Acceptance tests and handover to operations completeMandatory
- Open commitments listed with a plan to close themMandatory
- Deliverable-linked payments settledMandatory
- Pilot run with no critical or high findingsMandatory
- Users trained
- Launch rollback plan
Required documents
2 of 4 approved
- Deliverable completion certificatesNot submitted
- Project closure & handover formApproved · V1
- Lessons-learned logApproved · V1
- Benefits measurement planNot submitted
Criteria and score
Go from 75, conditional from 60; a mandatory criterion is met from 70.
Deliverables acceptedweight 35%Not met
Awaiting evidence from the project team.
Quality & securityweight 25%Met
Awaiting evidence from the project team.
Operations & handover readinessweight 25%Met
Awaiting evidence from the project team.
User & training readinessweight 15%
Awaiting evidence from the project team.
Approvers
Project Management Office
- Dr. Reem Al-QabbaniPMO directorVote pending
- Eng. Mazen KassabProject ownerVote pending
- Eng. Khaled Al-KayyaliProject sponsorVote pending