Government Cloud & Ministry Systems Migration
Add to watchlistBuilding the government cloud in the government data centre and moving the ministries’ systems and websites onto it in waves, retiring scattered servers.
Budget (BAC)
Actual cost
48% of budget
Progress
Estimate at completion
+SYP 40.2M
SPI · CPI
Forecast finish
21 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure8 January 2027
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate2 April 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionConditional goDate1 June 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate11 September 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate8 January 2027Closure · Not startedClosure · Not started
Scope statementRequired at this stage
What the project delivers, what it does not, and when a deliverable counts as accepted.
Building the government cloud in the government data centre and moving the ministries’ systems and websites onto it in waves, retiring scattered servers.
In scope
- Building the government cloud in the government data centre and moving the ministries’ systems and websites onto it in waves, retiring scattered servers.
- Migration from legacy systems
- ERP integration
Out of scope
- Operation and maintenance after the warranty period
- Work outside the approved site or system boundary
Acceptance criteria
- Main deliverable — stage 1Meets the approved specification, signed off by the project owner
- Main deliverable — final stageMeets the approved specification, signed off by the project owner
Scope baselineRequired at this stage
Every approved change creates a new baseline
- 1
SB-1Current2025-07-02
Baseline approved at the planning gate
BudgetSYP1.3BFinish2027-02-28
Requirements registerRequired at this stage
6 requirements of five kinds, with the trace status of each
By type
- Business1
- Functional1
- Technical2
- Regulatory1
- Security1
Fully traced
100%
6/6 · linked to a deliverable, task and test
Test passed
33%
2/6 · test result is a pass
Accepted
33%
2/6 · signed off by the business owner
Display options
| REQ-009-01 | One system for the procedures | Business | Must | In progress | Eng. Mazen KassabEng. Mazen KassabDirector General, Government Digital InfrastructureP-017mazen.kassab@psa.gov.sy | SB-1 | |
| REQ-009-02 | Historical data migration | Technical | Must | In progress | Eng. George HaddadEng. George HaddadDirector, Data Centres & Government NetworkP-024george.haddad@psa.gov.sy | SB-1 | |
| REQ-009-03 | Ready operational reports | Functional | Must | Approved | Eng. Mazen KassabEng. Mazen KassabDirector General, Government Digital InfrastructureP-017mazen.kassab@psa.gov.sy | SB-1 | |
| REQ-009-04 | ERP integration | Technical | Should | In progress | Eng. George HaddadEng. George HaddadDirector, Data Centres & Government NetworkP-024george.haddad@psa.gov.sy | SB-1 | |
| REQ-009-05 | Data classification | Regulatory | Should | In progress | Eng. Mazen KassabEng. Mazen KassabDirector General, Government Digital InfrastructureP-017mazen.kassab@psa.gov.sy | SB-1 | |
| REQ-009-06 | Identity and access management | Security | Could | In progress | Eng. George HaddadEng. George HaddadDirector, Data Centres & Government NetworkP-024george.haddad@psa.gov.sy | SB-1 |
Traceability matrixRequired at this stage
Requirement → deliverable → task → test → acceptance. No requirement has a gap.