PRJ-2026-001Off track4ExecutionHybridStalledDelivered by:Ministry of Finance

Integrated Public Financial Management System — Phase 1

Remove from watchlist

One system for budget preparation and execution, government accounting and payroll across the ministries — it ties investment spending to the plan’s projects and gives the Ministry of Finance and the Authority a daily view of spend.

Early warning: ⁦86%⁩ chance of slipping within ⁦30⁩ days

Budget (BAC)

SYP 1.6B

Actual cost

SYP 1.1B

⁦69%⁩ of budget

Progress

⁦61%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SYP 1.8B

+SYP 219.9M

SPI · CPI

0.82Schedule performance index · 0.820.88Cost performance index · 0.88

Forecast finish

⁦2027-02-27⁩

58 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure4 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate13 November 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate12 January 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate7 May 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate4 November 2026Closure · Not startedClosure · Not started

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

−23

May to October 2026

No material change in the health dimensions over the period.

AI insight

⁦86%⁩ chance of a further slip within ⁦30⁩ days

From the SPI trend (⁦0.82⁩), the task closure rate and the open risks, the early-warning engine expects another slip unless the resource gap is closed.

Confidence⁦82%⁩

Copilot summary

Generated from the live project data

The project is behind plan: ⁦61% done against 74% planned⁩.

⁦SPI 0⁩.⁦82⁩, ⁦CPI 0⁩.⁦88⁩.

The project’s link, progress and status

How the project ties to the strategy, its progress counted from accepted deliverables, and its status history.

Strategic link

The main objective and initiative, the secondary links, and the project’s contribution to its initiative.

Main strategic objective· Axis: Governance & Digital TransformationSO-5.2Sound governance and effective follow-up of projects and data

Main initiative

SI-1.1.1Integrated government financial systems

Contribution to the initiative⁦72%⁩

The project’s share of the initiative’s project budget (3 projects)

Secondary links

Annual work-plan line
WP-2025-001
Classification
Operational

Project progress from accepted deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate; nothing counts before acceptance.

Counted

⁦61%⁩

Awaiting acceptance ⁦11%⁩

Not handed in ⁦28%⁩

6 deliverables accepted

  • Release 1⁦16%⁩
  • Release 2⁦16%⁩
  • Business requirements⁦10%⁩
  • Solution design⁦10%⁩
  • Project plan & baseline⁦5%⁩
  • Monitoring & reporting⁦4%⁩

1 deliverable under inspection or acceptance

  • Integrations⁦11%⁩

Corrective planCP-2026-05

Sent back

Customisations and integrations missed in the tender book, the ministries’ payroll link failing twice, and late migration of historical financial data

Actions

⁦1⁩ of ⁦4⁩ done

Next: A joint fix session with the ministries’ payroll teams · Nour Al-Jabiri · 2026-10-30

Days won back

⁦10⁩ of ⁦32⁩

With the plan: 2027-02-27

Open the plan

Progress & earned value

⁦3⁩ of ⁦5⁩ milestones complete

Earned-value curve

Planned, earned and actual to the data date, cumulative, with the forecast cost tail

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Budget & commitments

Commitments are ⁦81%⁩ of budget

SYP1.1B/ SYP1.6BSYP219.9Mprojected overrun(⁦13.6%⁩)
Actual spend
SYP1.1B
Committed
SYP1.3B
Approved budget
SYP1.6B
Estimate at completion
SYP1.8B

Next milestones

  • Provisional acceptance⁦2026-12-18⁩was ⁦2026-11-04⁩Late
  • Closure⁦2027-02-27⁩was ⁦2026-12-31⁩Late

Waiting on someone

⁦2⁩ approvals and ⁦2⁩ open actions on this project

Approvals & requests

From «My actions» for this project

Actions

⁦2⁩ open

  • Re-baseline the plan per committee commentsNour Al-JabiriIn 7 days2026-11-04High
  • Joint fix workshop with the ministries’ payroll teamsEng. Rita GhanemIn 2 days2026-10-30High

Risks & impediments

3 open risks, exposure SYP 245M

Risk map

Probability
5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩Probability: Almost certain · Impact: SevereCritical · Score ⁦25⁩
4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩1Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩RSK-0013Late migration and reconciliation of historical financial data1Probability: Likely · Impact: MajorHigh · Score ⁦16⁩RSK-0012Customisation and ministry-systems integration cost above the approved reserveProbability: Likely · Impact: SevereCritical · Score ⁦20⁩
3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩1Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩RSK-0014Implementation consultants’ contracts ending before go-liveProbability: Possible · Impact: MajorMedium · Score ⁦12⁩Probability: Possible · Impact: SevereHigh · Score ⁦15⁩
2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩Probability: Unlikely · Impact: SevereMedium · Score ⁦10⁩
1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
12345

Impact

  • Critical0
  • High1
  • Medium2
  • Low0

Deliverables

⁦6⁩ of ⁦11⁩ approved

  • Project plan & baseline001-D1 · V1 · CRT-001-01⁦5%⁩Nour Al-Jabiri2025-04-212025-04-21Approved
  • Monitoring & reporting001-D2 · V1 · CRT-001-02⁦4%⁩Rasha Al-Mudarres2025-06-222025-06-22Approved
  • Business requirements001-D3 · V1 · CRT-001-03⁦10%⁩Rasha Al-Mudarres2025-08-232025-08-23Approved
  • Solution design001-D4 · V1 · CRT-001-04⁦10%⁩Salma Al-Zaim2025-10-242025-10-24Approved
  • Release 1001-D5 · V1 · CRT-001-05⁦16%⁩Salma Al-Zaim2025-12-252025-12-25Approved
  • Release 2001-D6 · V1 · CRT-001-06⁦16%⁩Nour Al-Jabiri2026-02-252026-02-25Approved
  • Integrations001-D7 · V1⁦11%⁩Rasha Al-Mudarres184 days overdue2026-04-27In review
  • System testing001-D8 · V0⁦8%⁩Nour Al-Jabiri122 days overdue2026-06-28Draft
  • User acceptance testing001-D9 · V0⁦8%⁩Rasha Al-Mudarres60 days overdue2026-08-29Draft
  • Training & change001-D10 · V0⁦6%⁩Rasha Al-MudarresIn 2 days2026-10-30Draft
  • Go-live & handover001-D11 · V0⁦6%⁩Salma Al-ZaimIn 64 days2026-12-31Draft

Team, contracts & documents

Team

4 members

Nour Al-Jabiri · Director, Government Systems & IntegrationEng. Rita Ghanem · Enterprise ArchitectHuda Al-Dandal · Senior Financial Analyst — Investment Plan
  • Nour Al-JabiriNour Al-JabiriDirector, Government Systems & IntegrationProject managerP-025nour.aljabiri@psa.gov.sy⁦60%⁩
  • Eng. Rita GhanemEng. Rita GhanemEnterprise ArchitectPFM system solution architectureP-031rita.ghanem@psa.gov.sy⁦40%⁩
  • Huda Al-DandalHuda Al-DandalSenior Financial Analyst — Investment PlanFinancial analystP-037huda.aldandal@psa.gov.sy⁦10%⁩

Documents

  • No documents yet

Meetings

  • No meetings scheduled