PRJ-2026-001Off track4ExecutionHybridStalledDelivered by:Ministry of Finance

Integrated Public Financial Management System — Phase 1

Remove from watchlist

One system for budget preparation and execution, government accounting and payroll across the ministries — it ties investment spending to the plan’s projects and gives the Ministry of Finance and the Authority a daily view of spend.

Early warning: ⁦86%⁩ chance of slipping within ⁦30⁩ days

Budget (BAC)

SYP 1.6B

Actual cost

SYP 1.1B

⁦69%⁩ of budget

Progress

⁦61%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SYP 1.8B

+SYP 219.9M

SPI · CPI

0.82Schedule performance index · 0.820.88Cost performance index · 0.88

Forecast finish

⁦2027-02-27⁩

58 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure4 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate13 November 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate12 January 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate7 May 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate4 November 2026Closure · Not startedClosure · Not started
Fields required by the project’s stage (Execution): 15 fields required now.Field settings

Planning and Statistics Authority

Project charter

Integrated Public Financial Management System — Phase 1

APPROVEDV2Approved ⁦2025-01-10⁩

1Project identity

Required at this stage
Project name
Integrated Public Financial Management System — Phase 1
Project code
PRJ-2026-001
Project sponsor
Salma Al-ZaimSalma Al-ZaimDeputy President, Finance, Administration & the Investment PlanP-012salma.alzaim@psa.gov.sy
Project manager
Nour Al-JabiriNour Al-JabiriDirector, Government Systems & IntegrationP-025nour.aljabiri@psa.gov.sy
Project owner
Rasha Al-MudarresRasha Al-MudarresDirector General, Finance & ContractsP-018rasha.almudarres@psa.gov.sy
Portfolio & programme
Government Digital Infrastructure & Systems PortfolioIntegrated Government Systems Programme
Type & methodology
IT · Hybrid
Current phase
4Execution

2Background & rationale

Required at this stage

One system for budget preparation and execution, government accounting and payroll across the ministries — it ties investment spending to the plan’s projects and gives the Ministry of Finance and the Authority a daily view of spend.

3Objectives

Required at this stage
  1. 1Sound governance and effective follow-up of projects and data
  2. 2Stimulate growth, restore production and attract investment

4Scope

Required at this stage

In scope

  • One system for budget preparation and execution, government accounting and payroll across the ministries — it ties investment spending to the plan’s projects and gives the Ministry of Finance and the Authority a daily view of spend.
  • Migration from legacy systems
  • ERP integration

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

5High-level requirements

Required at this stage
  1. 1Migration from legacy systems
  2. 2ERP integration
  3. 3National cybersecurity controls

6Deliverables

Required at this stage
1Project management plan⁦2025-02-10⁩
2Main deliverable — stage 1⁦2026-01-13⁩
3Main deliverable — final stage⁦2026-09-21⁩
4Final report⁦2026-12-31⁩

7Key milestones

Required at this stage
  1. Charter approved⁦2025-01-10⁩
  2. Contract signed⁦2025-05-07⁩
  3. 50% of works complete⁦2026-01-13⁩
  4. Provisional acceptance⁦2026-11-04⁩
  5. Closure⁦2026-12-31⁩

8Budget

Required at this stage
  • Main contract⁦71.9%⁩SYP1.2B
  • Supervision & consulting⁦14.1%⁩SYP227.5M
  • Internal team⁦9.0%⁩SYP145M
  • Contingency reserve (⁦5%⁩)⁦5.0%⁩SYP80M
The delivering body’s investment-plan allocationsTotalSYP1.6B

9Timeline

Required at this stage
Start
2025-01-1212 January 2025
Baseline finish
2026-12-3131 December 2026
Duration
⁦24⁩ months

10Key risks

Required at this stage
  • HighCustomisation and ministry-systems integration cost above the approved reserve
  • MediumLate migration and reconciliation of historical financial data
  • MediumImplementation consultants’ contracts ending before go-live

11Constraints

Required at this stage
  • Stay within the approved budget
  • Comply with the unified contracts law (⁦Law 51 of 2004⁩)

12Assumptions

Required at this stage
  • Named internal staff available throughout
  • Approvals land within the workflow’s action time limits

13Stakeholders

Required at this stage
  • Project sponsorDecisions and funding
  • Project ownerAccepts deliverables, owns benefits
  • National Project Management Office (PMO)Governance and compliance

14Success criteria

Required at this stage
  1. 1Delivered within the approved budget
  2. 2On the approved date ⁦±5%⁩
  3. 3⁦Target benefits within 12 months⁩

15Governance structure

Required at this stage
  • Change CommitteeApproves scope, cost and schedule changesWeekly
  • Project Approval CommitteeMethodology compliance, data quality, stage gatesFortnightly
  • Project management teamDay-to-day control, risks, impediments, the periodic update cardWeekly
Version V2 · ⁦4⁩ of ⁦4⁩ signaturesInternal — not for circulation outside the Authority