Integrated Public Financial Management System — Phase 1
Remove from watchlistOne system for budget preparation and execution, government accounting and payroll across the ministries — it ties investment spending to the plan’s projects and gives the Ministry of Finance and the Authority a daily view of spend.
Budget (BAC)
Actual cost
69% of budget
Progress
Estimate at completion
+SYP 219.9M
SPI · CPI
Forecast finish
58 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure4 November 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionConditional goDate13 November 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionConditional goDate12 January 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate7 May 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate4 November 2026Closure · Not startedClosure · Not started
Closure readiness
Closure planned after the forecast finish on 2027-02-27
A preview of what closure will need, with the planned dates, and the lessons captured so far.
Closure checklist
Seven mandatory items before any project closes.
- 1
Deliverables acceptedNot started
Final acceptance of every deliverable
Rasha Al-MudarresPlanned 2027-02-17
- 2
Financial closureNot started
Spend reconciled, commitments closed
Omar Al-NahhasPlanned 2027-03-19
- 3
Contract closureNot started
Contracts closed, bonds released
Omar Al-NahhasPlanned 2027-03-29
- 4
Documents archivedNot started
Documents archived with classification
Nour Al-JabiriPlanned 2027-03-24
- 5
Lessons learnedNot started
Lessons-learned session
Nour Al-JabiriPlanned 2027-03-14
- 6
Benefits owner assignedNot started
Benefits handed to their owner with a measurement plan
Rasha Al-MudarresPlanned 2027-03-09
- 7
Final report approvedNot started
Final report and its approval
Nour Al-JabiriPlanned 2027-04-03
Post-implementation review
Did it reach its goal? Did it stay on budget? Were the benefits realised? What did we learn and improve?
The review comes after closure
About three months after the forecast finish (2027-02-27), with the sponsor and the benefits owner.
Lessons learned
0 lessons — offered automatically to similar projects when they are created.
No lessons captured yet
Capture what the team learned during delivery; closure needs at least one.
Benefits handover
Each benefit moves from the project manager to an owner who measures it after closure.
No benefits recorded for this project.