Programme · PG-04 · Government Digital Infrastructure & Systems Portfolio

Integrated Government Systems Programme

Off track

The public financial management system, civil registry automation, e-archiving and employee self-service.

Approved budget
SYP 3B

incl. SYP 100M programme reserve

Actual spend
SYP 1.8B

⁦60%⁩ of budget

EAC
SYP 3.1B+7.1%

Estimate at completion

Progress
⁦62%⁩

Planned ⁦68%⁩

Schedule performance index
0.89

Cost performance index 0.94

Manager

Nour Al-Jabiri

Director, Government Systems & Integration

Sponsor

Salma Al-Zaim

Deputy President, Finance, Administration & the Investment Plan

Projects

4 projects

2024-05-05 — 2027-12-30

On track 2At risk 1Off track 1

Programme objectives

What the programme must achieve, and the strategic objectives it serves.

  1. 1

    One public financial management system for budget, procurement, payroll and accounting across the ministries

  2. 2

    An automated civil registry linked to the civil-registry offices in the governorates

  3. 3

    Self-service for 90% of public employees’ transactions

Programme benefits

From baseline to target

  • Spend-rationalisation savings

    by ⁦2027⁩
    Baseline 0Current 1.5 SYP bnTarget 2.1
  • Staff hours saved by automation

    by ⁦2027⁩
    Baseline 0Current 3,450 hoursTarget 3,600

Roadmap

One lane per project: start to forecast finish, with the progress earned and the baseline finish.

EarnedRemainingBaseline finishSlip
2024202520262027
2025-09-21
2027-02-27
2026-11-15
2027-12-30

Dependencies between projects

What waits on what. Red links are on the programme’s critical path.

Critical path

What each project needs from the one before

  • Critical

    Civil registry automation reads fees and payments from the financial management system

  • Self-service processes fold into the payroll & HR module

  • Payment documents archived electronically at the Ministry of Finance

Shared risks

Risks that hit more than one project, managed at programme level.

16

Late historic-data migration delays the financial close and civil registry automation

PRK-04-1·Mitigate·Nour Al-Jabiri

Affects
9

Resistance from users of paper processes in the ministries

PRK-04-2·Mitigate·Ola Al-Jandali

Affects

Open risks in the programme’s projects

4 risks

Open risks in the programme’s projects
  • Critical0
  • High1
  • Medium3
  • Low0
  • Risks 4
Probability
5
4
3
2
1
12345

Impact

Open risks in the programme’s projects
Probability \ Impact12345
50 · Low0 · Medium0 · High0 · Critical0 · Critical
40 · Low0 · Medium1 · Medium1 · High0 · Critical
30 · Low0 · Low2 · Medium0 · Medium0 · High
20 · Low0 · Low0 · Low0 · Medium0 · Medium
10 · Low0 · Low0 · Low0 · Low0 · Low

Programme KPIs · Stakeholders

Stakeholders

Power against interest; click a person to see their role.

Power

Keep satisfied0

Manage closely3

Monitor0

Keep informed1

Salma Al-ZaimManage closelyRasha Al-MudarresManage closelyIbrahim Al-SaeedManage closelyHuda Al-DandalKeep informed

Interest

Programme decisions

What the committees decided on the programme’s projects, and what the programme raised to them.

Committees

National Projects Steering Committee

Monthly · Quorum ⁦5⁩

Dr. Ziad Al-Atassi · Deputy President, Strategy & PerformanceEng. Abdulrahman Al-Kilani · Deputy President, Development Projects Follow-upEng. Khaled Al-Kayyali · Deputy President, Digital Transformation
Chair: Dr. Samer Al-DaqqarNext meeting 2026-11-03
Project Approval Committee

Fortnightly · Quorum ⁦4⁩

Basel Al-Mahayni · Director General, Digital Government Services & Portfolio Manager, Digital Government Services & DataDr. Mais Al-Sibai · Director General, Strategy & National ProjectsNizar Abu Fakhr · Head, Monitoring, Evaluation & Performance
Chair: Dr. Reem Al-QabbaniNext meeting 2026-11-04
Change Committee

Weekly · Quorum ⁦4⁩

Dr. Reem Al-Qabbani · Director, National Project Management OfficeOmar Al-Nahhas · Senior Finance & Contracts SpecialistRasha Al-Mudarres · Director General, Finance & Contracts
Chair: Dr. Ziad Al-AtassiNext meeting 2026-10-29

Programme projects

The programme’s performance is computed from these projects.

⁦4⁩ results
Export CSV
Manager
Integrated Public Financial Management System — Phase 1PRJ-2026-001Nour Al-Jabiri4ExecutionOff track⁦61%⁩SYP1.6BSYP1.8B⁦+13.6%⁩0.82Schedule performance index · 0.820.88Cost performance index · 0.88
Civil Registry Automation & Governorate Link-upPRJ-2026-011Nour Al-Jabiri3PlanningOn track⁦6%⁩SYP600MSYP600M⁦0.0%⁩1.00Schedule performance index · 1.001.00Cost performance index · 1.00
Ministry of Finance e-ArchivingPRJ-2026-017Nour Al-Jabiri5ClosureAt risk⁦95%⁩SYP355MSYP355M⁦0.0%⁩0.95Schedule performance index · 0.951.00Cost performance index · 1.00
Government HR System — Employee Self-ServicePRJ-2026-032Nour Al-Jabiri5ClosureOn track⁦100%⁩SYP285MSYP268.9M⁦−5.7%⁩1.00Schedule performance index · 1.001.06Cost performance index · 1.06
Total · 4SYP2.9BSYP3.1B
⁦1⁩–⁦4⁩ of ⁦4⁩

Budget shares

Budget shares

SYP 2.9B

Budget

  • Integrated Public Financial Management System — Phase 1SYP 1.6B⁦57%⁩
  • Civil Registry Automation & Governorate Link-upSYP 600M⁦21%⁩
  • Ministry of Finance e-ArchivingSYP 355M⁦12%⁩
  • Government HR System — Employee Self-ServiceSYP 285M⁦10%⁩
Budget shares
CategoryValueShare
Integrated Public Financial Management System — Phase 1SYP 1.6B⁦57%⁩
Civil Registry Automation & Governorate Link-upSYP 600M⁦21%⁩
Ministry of Finance e-ArchivingSYP 355M⁦12%⁩
Government HR System — Employee Self-ServiceSYP 285M⁦10%⁩
TotalSYP 2.9B⁦100%⁩