PRJ-2026-001Off track4ExecutionHybridStalledDelivered by:Ministry of Finance
Integrated Public Financial Management System — Phase 1
Remove from watchlist
One system for budget preparation and execution, government accounting and payroll across the ministries — it ties investment spending to the plan’s projects and gives the Ministry of Finance and the Authority a daily view of spend.
Early warning: 86% chance of slipping within 30 days
Budget (BAC)
SYP 1.6B
Actual cost
SYP 1.1B
69% of budget
Progress
61%Awaiting acceptance 11%
Estimate at completion
SYP 1.8B
+SYP 219.9M
SPI · CPI
0.82Schedule performance index · 0.820.88Cost performance index · 0.88
Forecast finish
2027-02-27
58 days behind baseline
Execution·Stage 4 of 5
Next gate:Closure4 November 2026
Pre-start · CompletePre-start · Complete
Gate into «Initiation»DecisionConditional goDate13 November 2024Initiation · CompleteInitiation · Complete
Gate into «Planning»DecisionConditional goDate12 January 2025Planning · CompletePlanning · Complete
Gate into «Execution»DecisionGoDate7 May 2025Execution · Current stageExecution · Current stage
Gate into «Closure»DecisionNot held yetDate4 November 2026Closure · Not startedClosure · Not started
Schedule & Gantt
The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.
Finish-date drift
+58 days vs approved
Baseline (original = approved)2026-12-31
Current forecast2027-02-27
By earned schedule2028-03-04
Critical activities
6
of 8 open activities
Late activities
5
past their baseline finish
Schedule performance
0.62
earned ÷ planned value
Next milestone
in 30 days
Build complete
Layers
Compare with
Expand allCollapse all
ActivityOwnerForecast finishProgress
2025
2026
2027
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Jan
Feb
Mar
Apr
May
Today
2027-02-2761%
Integrated Public Financial Management System — Phase 1Planned: 2025-01-12 → 2026-12-31Forecast: 2025-01-12 → 2027-02-27Float: 0d