PRJ-2026-001Off track4ExecutionHybridStalledDelivered by:Ministry of Finance

Integrated Public Financial Management System — Phase 1

Remove from watchlist

One system for budget preparation and execution, government accounting and payroll across the ministries — it ties investment spending to the plan’s projects and gives the Ministry of Finance and the Authority a daily view of spend.

Early warning: ⁦86%⁩ chance of slipping within ⁦30⁩ days

Budget (BAC)

SYP 1.6B

Actual cost

SYP 1.1B

⁦69%⁩ of budget

Progress

⁦61%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SYP 1.8B

+SYP 219.9M

SPI · CPI

0.82Schedule performance index · 0.820.88Cost performance index · 0.88

Forecast finish

⁦2027-02-27⁩

58 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure4 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate13 November 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate12 January 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate7 May 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate4 November 2026Closure · Not startedClosure · Not started

Finance & earned value

The full budget structure, cost broken down by eight dimensions, cash flow with its S-curve, and earned-value indicators with an automatic end-of-project forecast.

Budget anatomy

The approved SYP 1.6B split into spent, committed and left, with the estimate at completion

Forecast overrun SYP 219.9M
EAC SYP 1.8B
Revised request SYP 1.8B
  • Actual spendSYP 1.1B
  • Committed, not spentSYP 192.2M
  • Allotted, uncommittedSYP 254.1M
  • Contingency availableSYP 48.4M

Budget

EstimatedManualFrom the project proposal — not from the finance systemthe proposal’s cost before approval
SYP 1.4B
Original budgetwhen the first baseline was approved
SYP 1.6B
Approved budgetafter approved change requests
SYP 1.6B
Current budgetavailable to spend now
SYP 1.6B
Revised budgetif the pending changes are approved
SYP 1.8B

Commitments

CommitmentsSyncedFrom the nightly finance-system syncsigned contracts and purchase orders
SYP 1.3B
Contracts1 active contract
SYP 1B
Purchase orders⁦3⁩ orders
SYP 280M
Remaining budgetapproved less actual
SYP 494.7M

Spend & outlook

Actual costSyncedFrom the nightly finance-system syncincluding accruals
SYP 1.1B
Accrualswork done, not yet invoiced
SYP 44.7M
Estimate at completionManualThe project manager’s estimate — not from the finance systemthe PM’s bottom-up forecast
SYP 1.8B
ContingencySYP 32.3M drawn of SYP 80.6M
SYP 48.4M

Estimated vs approved budget

What the project proposal estimated before approval, against today’s approved budget and the estimate at completion

EstimatedSYP 1.4B
ApprovedSYP 1.6B
Estimate at completionSYP 1.8B
Approved is SYP 177.5M (⁦12.4%⁩) above the estimate
The estimate at completion is SYP 397.4M (⁦27.7%⁩) above the estimate

From the «project proposal & feasibility study» approved at the approval gate on ⁦2024-10-29⁩ · The gap between estimated and approved comes from the scope update and the change requests approved after the approval gate.

ERP link — data readiness

The link keys are ready for the finance-system sync; Munjaz follows the project and does not replace the accounting system

⁦4⁩ of ⁦4⁩ fields ready
  • Cost centreCC-61001
  • WBS elements⁦5⁩ elements · P-2026-001.01 …
  • Purchase orders⁦3⁩ synced · ⁦0⁩ manual
  • Invoices & certificates⁦13⁩ posted · ⁦0⁩ in approval
Last sync⁦2026-10-28⁩ · 06:00 · succeededNext tonight at 02:00

Where each figure comes from

  • EstimatedManualFrom the project proposal — not from the finance system
  • CommitmentsSyncedFrom the nightly finance-system sync
  • Actual costSyncedFrom the nightly finance-system sync
  • Estimate at completionManualThe project manager’s estimate — not from the finance system

Once the link is live, synced figures are read from the finance system; manual updates stay available to the same roles and are logged.

Purchase-order register

Manual edit log

Every manual update — who, when, why and from which source

No manual edits on this project

All its figures come from the finance-system sync. Finance & procurement — and the project manager, for the estimate at completion — can update them by hand.

Budget bridge

From the original to the revised request

  • Total
  • Increase
  • Decrease

Contingency draw-downs

SYP 32.3M drawn of SYP 80.6M

  • Covering realised delivery risks⁦2026-08-29⁩SYP 32.3M

Purchase orders

Cost breakdown structure

Every dimension adds up to the same totals

Cost breakdown structure — WBS
ItemBudgetSYP MCommittedSYP MActualSYP MEACSYP MVarianceSYP MConsumption
1Management & governance125.13146.59146.59146.59⁦−21.46⁩
2Analysis & design265.90311.51311.51311.51⁦−45.60⁩
3Build625.65659.66659.66659.66⁦−34.01⁩
4Testing & acceptance312.83109.850.00394.54⁦−81.71⁩
5Launch & handover234.6282.390.00295.90⁦−61.29⁩
Unallocated contingency48.380.000.0024.19⁦+24.19⁩
Total1,612.501,310.001,117.761,832.39⁦−219.89⁩

Budget split

WBS

SYP 1.6B

Budget

  • Management & governanceSYP 125.1M⁦8%⁩
  • Analysis & designSYP 265.9M⁦16%⁩
  • BuildSYP 625.7M⁦39%⁩
  • Testing & acceptanceSYP 312.8M⁦19%⁩
  • Launch & handoverSYP 234.6M⁦15%⁩
  • Unallocated contingencySYP 48.4M⁦3%⁩

Cash flow

Planned, committed, actual and forecast

Spend per period

SYP millions

  • Planned
  • Actual
  • Forecast

Cumulative S-curve

Cumulative to close

  • Actual, then forecast
  • Planned, cumulative
  • Committed, cumulative
  • Forecast

Earned value management

At the data date ⁦2026-10-28⁩

Planned value, earned value and actual cost

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Finish by earned schedule

⁦2028-03-04⁩+429

SPI(t) ⁦0.63⁩ against the approved finish ⁦2026-12-31⁩

Planned valuePV
SYP 1.6B
The value of the work that should be done by today.
PV
Earned valueEV
SYP 983.6M
The value of the work actually done, at plan prices.
EV = % complete × BAC
Actual costAC
SYP 1.1B
What has actually been spent on the work done.
AC
Budget at completionBAC
SYP 1.6B
The approved budget for the whole project.
BAC
Cost varianceCV
⁦−134.13⁩ SYP M
Earned less actual; negative means paying more than the value.
CV = EV − AC
Schedule varianceSV
⁦−597.15⁩ SYP M
Earned less planned; negative means behind, in value.
SV = EV − PV
Cost performance indexCPI
0.88
Value produced per pound spent; under 1 is an overrun.
CPI = EV ÷ AC
Schedule performance indexSPI
0.62
Work done over work planned; under 1 is behind.
SPI = EV ÷ PV
Estimate at completionEAC
SYP 1.8B
What the project will cost when it finishes, as forecast.
EAC = BAC ÷ CPI
Estimate to completeETC
SYP 714.6M
What is still to be spent to completion.
ETC = EAC − AC
Variance at completionVAC
⁦−219.89⁩ SYP M
Budget less the estimate; negative is an overrun.
VAC = BAC − EAC
To-complete performance indexTCPI
1.27
The cost efficiency the rest must reach to stay on budget.
TCPI = (BAC − EV) ÷ (BAC − AC)

Automatic end-of-project forecast

Four ways to estimate the final cost, and the date earned schedule points to

  • At today’s cost performanceSYP 1.8B
  • If the rest goes to planSYP 1.7B
  • At cost and schedule performanceSYP 2.3B
  • The PM’s bottom-up estimateSYP 1.8B
  • To stay within SYP 1.6B, cost performance on the rest must rise to ⁦1.27⁩ — above what has been achieved.

Estimate at completion at that performance

SYP 1.8B

Variance at completion: ⁦−219.89⁩ SYP M