PRJ-2026-001Off track4ExecutionHybridStalledDelivered by:Ministry of Finance

Integrated Public Financial Management System — Phase 1

Remove from watchlist

One system for budget preparation and execution, government accounting and payroll across the ministries — it ties investment spending to the plan’s projects and gives the Ministry of Finance and the Authority a daily view of spend.

Early warning: ⁦86%⁩ chance of slipping within ⁦30⁩ days

Budget (BAC)

SYP 1.6B

Actual cost

SYP 1.1B

⁦69%⁩ of budget

Progress

⁦61%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SYP 1.8B

+SYP 219.9M

SPI · CPI

0.82Schedule performance index · 0.820.88Cost performance index · 0.88

Forecast finish

⁦2027-02-27⁩

58 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure4 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate13 November 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate12 January 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate7 May 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate4 November 2026Closure · Not startedClosure · Not started

Work breakdown structure

The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.

Structure levels

Pick a level to open the tree to that depth

Allotted to workSYP1.6B⁦16⁩ elements
Unallocated contingencySYP48.4MSYP 80.6M
Budget at completionSYP1.6BPRJ-2026-001
Weighted progress⁦61%⁩Linked deliverables: 0
ElementLevelOwnerDurationStart – finishProgressBudgetSYP MActualSYP MLinksDeliverables
Project776⁦2025-01-12⁩⁦2027-02-27⁩⁦61%⁩1,564.131,117.76—
1
Phase257⁦2025-01-12⁩⁦2025-09-26⁩⁦100%⁩125.13146.59—
1.1
WBS element158⁦2025-01-12⁩⁦2025-06-19⁩⁦100%⁩62.5773.300 / 1
1.2
WBS element158⁦2025-04-21⁩⁦2025-09-26⁩⁦100%⁩62.5773.301 / 2
2
Phase257⁦2025-07-29⁩⁦2026-04-12⁩⁦100%⁩265.90311.51—
2.1
WBS element158⁦2025-07-29⁩⁦2026-01-03⁩⁦100%⁩132.95155.751 / 1
2.2
WBS element158⁦2025-11-05⁩⁦2026-04-12⁩⁦100%⁩132.95155.751 / 2
3
Phase313⁦2026-01-18⁩⁦2026-11-27⁩⁦90%⁩625.65659.66—
3.1
WBS element158⁦2026-02-12⁩⁦2026-07-20⁩⁦100%⁩208.55244.321 / 1
3.2
WBS element158⁦2026-05-22⁩⁦2026-10-27⁩⁦100%⁩208.55244.321 / 1
3.3
WBS element313⁦2026-01-18⁩⁦2026-11-27⁩⁦70%⁩208.55171.021 / 2
4
Phase60⁦2026-11-13⁩⁦2027-01-12⁩⁦0%⁩312.83——
4.1
WBS element37⁦2026-11-13⁩⁦2026-12-20⁩⁦0%⁩156.41—1 / 1
4.2
WBS element37⁦2026-12-06⁩⁦2027-01-12⁩⁦0%⁩156.41—1 / 2
5
Phase60⁦2026-12-29⁩⁦2027-02-27⁩⁦0%⁩234.62——
5.1
WBS element37⁦2026-12-29⁩⁦2027-02-04⁩⁦0%⁩117.31—1 / 1
5.2
WBS element37⁦2027-01-21⁩⁦2027-02-27⁩⁦0%⁩117.31—1 / 1
Total⁦61%⁩1,564.131,117.76