Original
Original baseline
- Finish
- 2026-12-31
- Budget
- SYP 1.6B
- 16 activities
Approved with the project plan at the planning gate.
Approved 2025-01-12 · by Salma Al-Zaim
One system for budget preparation and execution, government accounting and payroll across the ministries — it ties investment spending to the plan’s projects and gives the Ministry of Finance and the Authority a daily view of spend.
Budget (BAC)
Actual cost
69% of budget
Progress
Estimate at completion
+SYP 219.9M
SPI · CPI
Forecast finish
58 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure4 November 2026
The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.
Original
Approved with the project plan at the planning gate.
Approved 2025-01-12 · by Salma Al-Zaim
Working
Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.
Created 2026-10-28 · by Nour Al-Jabiri
What changed from version A to version B
Finish
2026-12-312027-02-27
+58 days
Budget
SYP 1.6BSYP 1.8B
+170.00 SYP M
Milestones moved
5 / 5
Each line starts at the milestone’s date in A and ends at its date in B
Version AVersion B
Difference in SYP millions from A to B
Every saved version with its reason and reference