RSK-0014Integrated Public Financial Management System — Phase 1

Implementation consultants’ contracts ending before go-live

9MediumOpen

A risk's detail, response, contingency and residual risk.

Risk statement

From cause to event to impact — with the preventive controls before the event and the contingency after it

Cause

Scarce specialists and projects competing for the same people

Preventive controls

  • A resource plan signed by the programme manager
  • Train back-ups from the in-house team

2 / 2

Event

Implementation consultants’ contracts ending before go-live

9MediumTrigger

Any critical role vacant for over two weeks

Contingency

Bring in temporary outside resources

Impact

Lower productivity and later deliverables

SYP 22.5M

Assessment

The level before and after the response

Inherent

5
4
3
2
1
1
2
3
4
5
9Medium

Residual

5
4
3
2
1
1
2
3
4
5
2Low

Exposure

SYP 22.5M

Residual

⁦78⁩% off the score

Score trend

Last six months

  • Score
  • Target residual

Escalation path

Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the PMO director

Last reviewed 12 days ago · Outside the engine — below «high»

  1. Project manager

    Current level

    Nour Al-Jabiri

    Currently followed up here
  2. 2

    Programme manager

    Nour Al-Jabiri

  3. 3

    PMO director

    Dr. Reem Al-Qabbani

  4. 4

    Executive Council

    Dr. Samer Al-Daqqar

    By the PMO director’s decision

Mitigation plan

Each action with its owner and date — tick it off when complete

⁦0⁩ of ⁦2⁩ done
  • A resource plan signed by the programme manager

    Rasha Al-MudarresRasha Al-MudarresDirector General, Finance & ContractsP-018rasha.almudarres@psa.gov.sy
    In progressIn 48 days2026-12-15
  • Train back-ups from the in-house team

    Nour Al-JabiriNour Al-JabiriDirector, Government Systems & IntegrationP-025nour.aljabiri@psa.gov.sy
    Not startedIn 48 days2026-12-15

Trigger

Any critical role vacant for over two weeks

Contingency

Bring in temporary outside resources

Esc