CP-2026-03Version ⁦1⁩

Hama National Hospital Upgrade & Extension

Awaiting approvalCriticalOverdue: ⁦1⁩

One corrective plan: why the project slipped, the rule that triggered it, the actions, the days won back, approval and follow-up.

What triggered the plan

The project’s reading the day the rule fired, and today.

Detected on ⁦2026-09-01⁩

Slip past the baseline

At detection
131 days
Today
152 days
Limit
> 40

Schedule performance index

At detection
0.72
Today
0.70
Limit
< 0.85

A rule approved by the Project Approval Committee (PMO-2026/14), read automatically from the project’s data.

Days won back

The forecast finish without the plan, with it, and the difference.

  1. Baseline

    2026-12-31
  2. Without the plan

    2027-07-31

    +212 days

  3. With the plan

    2027-06-01

    +152 days

Wins back 60 days

Achieved so far: 0 days

Why it slipped

Unapproved finishing samples, a skilled-labour shortage at the MEP subcontractor, and the pricing dispute over variation 7

Corrective actions

Each action with its owner, date, status and the days it wins back; overdue ones are shaded.

⁦0⁩ of ⁦4⁩ done
  • Rule on the finishing samples or approve an equivalent

    Eng. Sara Al-BaraziEng. Sara Al-BaraziSenior Project Manager — Hospitals & Health FacilitiesP-022sara.albarazi@psa.gov.syACT-0311
    Overdue13 days overdue2026-10-15Wins back 25 days
  • Require the main contractor to supply replacement MEP labour

    Eng. Fadi Al-DroubiEng. Fadi Al-DroubiDirector General, Human Development ProjectsP-014fadi.aldroubi@psa.gov.sy
    Not startedIn 12 days2026-11-09Wins back 15 days
  • Prepare the claims file for the dispute board

    Eng. Sara Al-BaraziEng. Sara Al-BaraziSenior Project Manager — Hospitals & Health FacilitiesP-022sara.albarazi@psa.gov.syACT-0310
    In progressIn 9 days2026-11-06
  • Re-sequence the finishing to run in parallel in both wings

    Eng. Sara Al-BaraziEng. Sara Al-BaraziSenior Project Manager — Hospitals & Health FacilitiesP-022sara.albarazi@psa.gov.sy
    Not startedIn 33 days2026-11-30Wins back 20 days

Follow-up

The project’s readings after the plan was approved, with the PMO’s notes.

No readings yet; follow-up starts after approval.