Execution
Corrective plan
Actions, owners, dates and status
- Form no.
- PSA-PMO-F11
- Template edition
- 1.4
- Version
- V1
- Form date
- 2026-10-24
Auto-filled — Filled by the platform from the project record, not typed.
- Project code
- PRJ-2026-007
- Project
- Hama National Hospital Upgrade & Extension
- Portfolio
- Health, Education & Industrial Recovery Portfolio
- Sector
- Development Projects Follow-up Sector
- Sponsor
- Eng. Abdulrahman Al-Kilani
- Project manager
- Eng. Sara Al-Barazi
1Why the planAuto-filled
Slip when detected
131 days
SPI
0.72
Finish without the plan
2027-07-31
Finish with the plan
2027-06-01
Causes
Unapproved finishing samples, a skilled-labour shortage at the MEP subcontractor, and the pricing dispute over variation 7
2Actions
| Action | Owner | Due | Status | Days won back |
|---|---|---|---|---|
| Rule on the finishing samples or approve an equivalent | Eng. Sara Al-Barazi | 2026-10-15 | In progress | 25 |
| Require the main contractor to supply replacement MEP labour | Eng. Fadi Al-Droubi | 2026-11-09 | Not started | 15 |
| Prepare the claims file for the dispute board | Eng. Sara Al-Barazi | 2026-11-06 | In progress | 0 |
| Re-sequence the finishing to run in parallel in both wings | Eng. Sara Al-Barazi | 2026-11-30 | Not started | 20 |
| Total | — | — | — | 60 |
3Support requested
- Amount
- SYP 0
- Detail
- A decision to accept an equivalent finishing material on the consultant’s advice
4PMO follow-upAuto-filled
| Date | SPI | Slip | Note |
|---|---|---|---|
| No follow-up yet | |||
Approval logChain: Corrective plan approval · version 1
Every decision on the form — who, their role, the note and the time. It prints with the form.
| # | Step | Kind | Name | Decision | Note | Date & time |
|---|---|---|---|---|---|---|
| 1 | Author | — | Eng. Sara Al-BaraziSenior Project Manager — Hospitals & Health Facilities | Submitted | — | 2026-10-24 12:03 |
| 2 | Programme manager review | Technical acceptance | Approval engineProgramme manager | Pre-breach alert | — | 2026-10-27 08:00 |
Signatures
Programme manager review
Dr. Reem Al-Qabbani
Awaiting decision
National Projects Steering Committee approval
Dr. Samer Al-Daqqar
Later