Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية
PRJ-2026-033On hold3PlanningConstructionStoppedDelivered by:Ministry of Health

Al-Mayadin General Hospital

Add to watchlist

A general hospital in Al-Mayadin serving the eastern Deir ez-Zor countryside with emergency, surgery, paediatrics and maternity — paused until the governorate council completes the land allocation.

Budget (BAC)

SYP 5.3B

Actual cost

SYP 105M

⁦2%⁩ of budget

Progress

⁦2%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SYP 5.3B

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2028-12-31⁩

184 days behind baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution15 July 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate31 December 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate1 March 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate15 July 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close