PRJ-2026-033On hold3PlanningConstructionStoppedDelivered by:Ministry of Health

Al-Mayadin General Hospital

Add to watchlist

A general hospital in Al-Mayadin serving the eastern Deir ez-Zor countryside with emergency, surgery, paediatrics and maternity — paused until the governorate council completes the land allocation.

Budget (BAC)

SYP 5.3B

Actual cost

SYP 105M

⁦2%⁩ of budget

Progress

⁦2%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SYP 5.3B

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2028-12-31⁩

184 days behind baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution15 July 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate31 December 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate1 March 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate15 July 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Baselines

The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.

No baseline approved yet

The project is in Planning: the working plan is ready (⁦17 activities⁩, finish ⁦2029-01-05⁩, ⁦budget SYP 5⁩.⁦3B⁩). Save it as the first baseline and send it for approval; once approved it is locked and changes only through an approved change request.

  1. Working

    Working baseline

    v2.0-draftWorking draftVersion AVersion B
    Finish
    ⁦2029-01-05⁩
    Budget
    SYP 5.3B
    ⁦17⁩ activities

    The working plan before the first baseline: a snapshot of it is saved and sent for approval at the planning gate.

    Created ⁦2026-10-28⁩ · by Eng. Sara Al-Barazi

    Edit in the schedule

Compare two versions

What changed from version A to version B

No approved baseline yet — measured against the working plan

Version history

Every saved version with its reason and reference

  1. Working baselinev2.0-draftWorking draftThe working plan before the first baseline: a snapshot of it is saved and sent for approval at the planning gate.⁦2026-10-28⁩by Eng. Sara Al-Barazi
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close