Al-Mayadin General Hospital
Add to watchlistA general hospital in Al-Mayadin serving the eastern Deir ez-Zor countryside with emergency, surgery, paediatrics and maternity — paused until the governorate council completes the land allocation.
Budget (BAC)
Actual cost
2% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
184 days behind baseline
PlanningStage 3 of 5
Next gate:Execution15 July 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate31 December 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate1 March 2026Planning · Current stagePlanning · Current stage
- Gate into «Execution»DecisionNot held yetDate15 July 2026Execution · Not startedExecution · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2026-08-24 | 2027-02-15 | +175 days | Eng. Sara Al-BaraziEng. Sara Al-BaraziSenior Project Manager — Hospitals & Health FacilitiesP-022sara.albarazi@psa.gov.sy | Late | 0 | Not requested |
| Designs approvedMS-G2 | Project | 2027-01-06 | 2027-07-03 | +178 days | Eng. Sara Al-BaraziEng. Sara Al-BaraziSenior Project Manager — Hospitals & Health FacilitiesP-022sara.albarazi@psa.gov.sy | At risk | 0 | Not requested |
| Build completeMS-G3 | Contractual | 2027-07-28 | 2028-01-26 | +182 days | Eng. Sara Al-BaraziEng. Sara Al-BaraziSenior Project Manager — Hospitals & Health FacilitiesP-022sara.albarazi@psa.gov.sy | At risk | 0 | Not requested |
| Testing & acceptance completeMS-G4 | Regulatory | 2028-02-16 | 2028-08-20 | +186 days | Eng. Sara Al-BaraziEng. Sara Al-BaraziSenior Project Manager — Hospitals & Health FacilitiesP-022sara.albarazi@psa.gov.sy | At risk | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2028-06-30 | 2029-01-05 | +189 days | Eng. Sara Al-BaraziEng. Sara Al-BaraziSenior Project Manager — Hospitals & Health FacilitiesP-022sara.albarazi@psa.gov.sy | At risk | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
2%Awaiting acceptance
0%Not handed in
98%Deliverable flow
Display options
| Project plan & baseline033-D1 | 2% | CRT-033-01 | Approved | Eng. Sara Al-BaraziEng. Sara Al-BaraziSenior Project Manager — Hospitals & Health FacilitiesP-022sara.albarazi@psa.gov.sy | Eng. Wassim Al-Azm | 2026-06-17 | V1 | 3 of 3 |
| Monitoring & reporting033-D2 | 3% | — | Draft | Eng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.sy | Eng. Wassim Al-Azm | 2026-08-24 | V0 | 0 of 3 |
| Detailed design033-D3 | 6% | — | Draft | Eng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.sy | Eng. Wassim Al-Azm | 2026-10-30 | V0 | 0 of 3 |
| Permits & approvals033-D4 | 6% | — | Draft | Eng. Bashir Al-TaiEng. Bashir Al-TaiDeputy President, Local Development & GovernoratesP-049bashir.altai@psa.gov.sy | Eng. Wassim Al-Azm | 2027-01-06 | V0 | 0 of 3 |
| Site works & excavation033-D5 | 13% | — | Draft | Eng. Bashir Al-TaiEng. Bashir Al-TaiDeputy President, Local Development & GovernoratesP-049bashir.altai@psa.gov.sy | Eng. Wassim Al-Azm | 2027-03-15 | V0 | 0 of 3 |
| Structure033-D6 | 13% | — | Draft | Eng. Sara Al-BaraziEng. Sara Al-BaraziSenior Project Manager — Hospitals & Health FacilitiesP-022sara.albarazi@psa.gov.sy | Eng. Wassim Al-Azm | 2027-05-21 | V0 | 0 of 3 |
| Finishes033-D7 | 13% | — | Draft | Eng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.sy | Eng. Wassim Al-Azm | 2027-07-28 | V0 | 0 of 3 |
| Supply033-D8 | 10% | — | Draft | Eng. Sara Al-BaraziEng. Sara Al-BaraziSenior Project Manager — Hospitals & Health FacilitiesP-022sara.albarazi@psa.gov.sy | Eng. Wassim Al-Azm | 2027-10-04 | V0 | 0 of 3 |
| Installation033-D9 | 10% | — | Draft | Eng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.sy | Eng. Wassim Al-Azm | 2027-12-10 | V0 | 0 of 3 |
| Testing & commissioning033-D10 | 10% | — | Draft | Eng. Bashir Al-TaiEng. Bashir Al-TaiDeputy President, Local Development & GovernoratesP-049bashir.altai@psa.gov.sy | Eng. Wassim Al-Azm | 2028-02-16 | V0 | 0 of 3 |
| Provisional acceptance033-D11 | 7% | — | Draft | Eng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.sy | Eng. Wassim Al-Azm | 2028-04-23 | V0 | 0 of 3 |
| Final acceptance033-D12 | 7% | — | Draft | Eng. Bashir Al-TaiEng. Bashir Al-TaiDeputy President, Local Development & GovernoratesP-049bashir.altai@psa.gov.sy | Eng. Wassim Al-Azm | 2028-06-30 | V0 | 0 of 3 |
| Total · 12 | 100% |