RSK-0044Al-Mayadin General Hospital
Late land allocation and registration by the Deir ez-Zor governorate council
A risk's detail, response, contingency and residual risk.
Latest escalation · ESC-2026-011
Executive Council
The Al-Mayadin hospital plot is registered to another public body; design and tender are on hold
Coordination· Asked from: Dr. Samer Al-Daqqar
A letter from the President of the Authority to the owning body and the Deir ez-Zor governor to complete the allocation
Risk statement
From cause to event to impact — with the preventive controls before the event and the contingency after it
Cause
The Al-Mayadin hospital plot is registered to another public body and its allocation to the Ministry of Health is incomplete
Preventive controls
- A letter from the President of the Authority to the Deir ez-Zor governor and the owning body
- Identify a fallback plot with the governorate council
1 / 2
Event
Late land allocation and registration by the Deir ez-Zor governorate council
No allocation decision by the end of December
Contingency
Move to the fallback site and adapt the design
Impact
Design and tender suspended; health services in rural eastern Deir ez-Zor stay in temporary facilities for at least six more months
Assessment
The level before and after the response
Inherent
Residual
Exposure
SYP 300M
Residual
55% off the score
Score trend
Last six months
- Score
- Target residual
Escalation path
Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the PMO director
Last reviewed 22 days ago
Project manager
Eng. Sara Al-Barazi
Currently followed up hereProgramme manager
Eng. Sara Al-Barazi
Automatically at 15 days unreviewed · threshold passed 7 days agoPMO director
Current levelDr. Reem Al-Qabbani
Automatically at 20 days unreviewed · threshold passed 2 days ago- 4
Executive Council
Dr. Samer Al-Daqqar
By the PMO director’s decision
Mitigation plan
Each action with its owner and date — tick it off when complete
A letter from the President of the Authority to the Deir ez-Zor governor and the owning body
Dr. Samer Al-DaqqarDr. Samer Al-DaqqarPresident, Planning and Statistics AuthorityP-001samer.aldaqqar@psa.gov.syDone2026-10-252026-10-25Identify a fallback plot with the governorate council
Eng. Sara Al-BaraziEng. Sara Al-BaraziSenior Project Manager — Hospitals & Health FacilitiesP-022sara.albarazi@psa.gov.syNot startedIn 48 days2026-12-15
Trigger
No allocation decision by the end of December
Contingency
Move to the fallback site and adapt the design