PRJ-2026-026On hold3PlanningWaterfallStoppedDelivered by:Ministry of Energy

Baniyas Pilot Seawater Desalination Plant

Add to watchlist

A pilot seawater desalination plant in Baniyas to test the technology and cost before scaling along the coast — paused while its allocation in the investment plan is confirmed.

Budget (BAC)

SYP 825M

Actual cost

SYP 66M

⁦8%⁩ of budget

Progress

⁦8%⁩Awaiting acceptance ⁦6%⁩

Estimate at completion

SYP 825M

SPI · CPI

0.89Schedule performance index · 0.891.00Cost performance index · 1.00

Forecast finish

⁦2027-10-31⁩

123 days behind baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution24 April 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 December 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate1 February 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate24 April 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

−19

May to October 2026

No material change in the health dimensions over the period.

Copilot summary

Generated from the live project data

The project is close to plan: ⁦8% done against 9% planned⁩.

⁦SPI 0⁩.⁦89⁩, ⁦CPI 1⁩.⁦00⁩.

The project’s link, progress and status

How the project ties to the strategy, its progress counted from accepted deliverables, and its status history.

Strategic link

The main objective and initiative, the secondary links, and the project’s contribution to its initiative.

Main strategic objective· Axis: Reconstruction & InfrastructureSO-2.1Rehabilitate core energy, water and transport infrastructure

Main initiative

SI-2.1.3Renewable energy & non-conventional water

Contribution to the initiative⁦26%⁩

The project’s share of the initiative’s project budget (2 projects)

Secondary links

No secondary links

Annual work-plan line
WP-2026-026
Classification
Operational

Project progress from accepted deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate; nothing counts before acceptance.

Counted

⁦8%⁩

Awaiting acceptance ⁦6%⁩

Not handed in ⁦86%⁩

2 deliverables accepted

  • Project plan & baseline⁦4%⁩
  • Monitoring & reporting⁦4%⁩

1 deliverable under inspection or acceptance

  • Detailed design⁦6%⁩

Progress & earned value

⁦2⁩ of ⁦5⁩ milestones complete

Earned-value curve

Planned, earned and actual to the data date, cumulative, with the forecast cost tail

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Budget & commitments

Commitments are ⁦9%⁩ of budget

SYP66M/ SYP825M
Actual spend
SYP66M
Committed
SYP77.5M
Approved budget
SYP825M
Estimate at completion
SYP825M

Next milestones

  • 50% of works complete⁦2026-12-22⁩was ⁦2026-10-21⁩Late
  • Provisional acceptance⁦2027-08-20⁩was ⁦2027-05-20⁩Late
  • Closure⁦2027-10-31⁩was ⁦2027-06-30⁩Late

Waiting on someone

⁦0⁩ approvals and ⁦1⁩ open action on this project

Approvals & requests

From «My actions» for this project

  • No approvals pending

Actions

⁦1⁩ open

  • ⁦Request the Baniyas pilot plant allocation in the 2027 investment plan⁩Huda Al-DandalIn 18 days2026-11-15Medium

Change requests

Cost and schedule impact

  • No change requests

Risks & impediments

1 open risk, exposure SYP 120M

Risk map

Probability
5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩Probability: Almost certain · Impact: SevereCritical · Score ⁦25⁩
4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩1Probability: Likely · Impact: MajorHigh · Score ⁦16⁩RSK-0043Allocation left out of the 2027 investment plan; tender stays on holdProbability: Likely · Impact: SevereCritical · Score ⁦20⁩
3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩Probability: Possible · Impact: MajorMedium · Score ⁦12⁩Probability: Possible · Impact: SevereHigh · Score ⁦15⁩
2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩Probability: Unlikely · Impact: SevereMedium · Score ⁦10⁩
1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
12345

Impact

  • Critical0
  • High1
  • Medium0
  • Low0

Open impediments

⁦0⁩ escalated

  • No open impediments

Deliverables

⁦2⁩ of ⁦12⁩ approved

  • Project plan & baseline026-D1 · V1 · CRT-026-01⁦4%⁩Eng. Rami Youssef2026-04-072026-04-07Approved
  • Monitoring & reporting026-D2 · V1 · CRT-026-02⁦4%⁩Eng. Wassim Al-Azm2026-05-182026-05-18Approved
  • Detailed design026-D3 · V1⁦6%⁩Eng. Wassim Al-Azm122 days overdue2026-06-28Submitted
  • Permits & approvals026-D4 · V0⁦6%⁩Salma Al-Zaim81 days overdue2026-08-08Draft
  • Site works & excavation026-D5 · V0⁦12%⁩Salma Al-Zaim41 days overdue2026-09-17Draft
  • Structure026-D6 · V0⁦12%⁩Eng. Rami YoussefDue today2026-10-28Draft
  • Finishes026-D7 · V0⁦12%⁩Eng. Wassim Al-AzmIn 41 days2026-12-08Draft
  • Supply026-D8 · V0⁦10%⁩Eng. Rami YoussefIn 82 days2027-01-18Draft
  • Installation026-D9 · V0⁦10%⁩Eng. Wassim Al-AzmIn 123 days2027-02-28Draft
  • Testing & commissioning026-D10 · V0⁦10%⁩Salma Al-ZaimIn 163 days2027-04-09Draft
  • Provisional acceptance026-D11 · V0⁦7%⁩Eng. Wassim Al-AzmIn 204 days2027-05-20Draft
  • Final acceptance026-D12 · V0⁦7%⁩Salma Al-ZaimIn 245 days2027-06-30Draft

Team, contracts & documents

Team

2 members

Eng. Rami Youssef · Director, Renewable Energy & Environment ProjectsAbdullah Al-Ujaili · Contracts & Tendering Specialist
  • Eng. Rami YoussefEng. Rami YoussefDirector, Renewable Energy & Environment ProjectsProject manager (on hold)P-028rami.youssef@psa.gov.sy⁦15%⁩
  • Abdullah Al-UjailiAbdullah Al-UjailiContracts & Tendering SpecialistPilot desalination plant tenderP-038abdullah.alujaili@psa.gov.sy⁦20%⁩

Contracts

0 contracts

  • No external contracts — delivered in-house

Documents

  • No documents yet

Meetings

  • No meetings scheduled
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close