Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية
PRJ-2026-026On hold3PlanningWaterfallStoppedDelivered by:Ministry of Energy

Baniyas Pilot Seawater Desalination Plant

Add to watchlist

A pilot seawater desalination plant in Baniyas to test the technology and cost before scaling along the coast — paused while its allocation in the investment plan is confirmed.

Budget (BAC)

SYP 825M

Actual cost

SYP 66M

⁦8%⁩ of budget

Progress

⁦8%⁩Awaiting acceptance ⁦6%⁩

Estimate at completion

SYP 825M

SPI · CPI

0.89Schedule performance index · 0.891.00Cost performance index · 1.00

Forecast finish

⁦2027-10-31⁩

123 days behind baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution24 April 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 December 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate1 February 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate24 April 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Finance & earned value

The full budget structure, cost broken down by eight dimensions, cash flow with its S-curve, and earned-value indicators with an automatic end-of-project forecast.

Budget anatomy

The approved SYP 825M split into spent, committed and left, with the estimate at completion

EAC SYP 825M
Revised request SYP 825M
  • Actual spendSYP 66M
  • Committed, not spentSYP 11.5M
  • Allotted, uncommittedSYP 722.8M
  • Contingency availableSYP 24.8M

Budget

EstimatedManualFrom the project proposal — not from the finance systemthe proposal’s cost before approval
SYP 792.5M
Original budgetwhen the first baseline was approved
SYP 825M
Approved budgetafter approved change requests
SYP 825M
Current budgetavailable to spend now
SYP 825M
Revised budgetif the pending changes are approved
SYP 825M

Commitments

CommitmentsSyncedFrom the nightly finance-system syncsigned contracts and purchase orders
SYP 77.5M
Contracts0 active contracts
SYP 0
Purchase orders⁦2⁩ orders
SYP 77.5M
Remaining budgetapproved less actual
SYP 759M

Spend & outlook

Actual costSyncedFrom the nightly finance-system syncincluding accruals
SYP 66M
Accrualswork done, not yet invoiced
SYP 2.6M
Estimate at completionManualThe project manager’s estimate — not from the finance systemthe PM’s bottom-up forecast
SYP 825M
ContingencySYP 16.5M drawn of SYP 41.3M
SYP 24.8M

Estimated vs approved budget

What the project proposal estimated before approval, against today’s approved budget and the estimate at completion

EstimatedSYP 792.5M
ApprovedSYP 825M
Estimate at completionSYP 825M
Approved is SYP 32.5M (⁦4.1%⁩) above the estimate
The estimate at completion is SYP 32.5M (⁦4.1%⁩) above the estimate

From the «project proposal & feasibility study» approved at the approval gate on ⁦2025-11-18⁩ · The gap between estimated and approved comes from the scope update and the change requests approved after the approval gate.

ERP link — data readiness

The link keys are ready for the finance-system sync; Munjaz follows the project and does not replace the accounting system

⁦4⁩ of ⁦4⁩ fields ready
  • Cost centreCC-51026
  • WBS elements⁦5⁩ elements · P-2026-026.01 …
  • Purchase orders⁦2⁩ synced · ⁦0⁩ manual
  • Invoices & certificatesNo certificates
Last sync⁦2026-10-28⁩ · 06:00 · succeededNext tonight at 02:00

Where each figure comes from

  • EstimatedManualFrom the project proposal — not from the finance system
  • CommitmentsSyncedFrom the nightly finance-system sync
  • Actual costSyncedFrom the nightly finance-system sync
  • Estimate at completionManualThe project manager’s estimate — not from the finance system

Once the link is live, synced figures are read from the finance system; manual updates stay available to the same roles and are logged.

Purchase-order register

Manual edit log

Every manual update — who, when, why and from which source

No manual edits on this project

All its figures come from the finance-system sync. Finance & procurement — and the project manager, for the estimate at completion — can update them by hand.

Budget bridge

From the original to the revised request

  • Total
  • Increase
  • Decrease

Contingency draw-downs

SYP 16.5M drawn of SYP 41.3M

  • Covering realised delivery risks⁦2026-08-29⁩SYP 16.5M

Purchase orders

Cost breakdown structure

Every dimension adds up to the same totals

Cost breakdown structure — WBS
ItemBudgetSYP MCommittedSYP MActualSYP MEACSYP MVarianceSYP MConsumption
1Management & governance48.0249.6249.6249.62⁦−1.61⁩
2Design & permits96.0317.6216.3897.20⁦−1.17⁩
3Civil works304.104.750.00308.54⁦−4.45⁩
4MEP works240.083.750.00243.59⁦−3.51⁩
5Handover112.041.750.00113.67⁦−1.64⁩
Unallocated contingency24.750.000.0012.38⁦+12.38⁩
Total825.0077.5066.00825.00⁦+0.00⁩

Budget split

WBS

SYP 825M

Budget

  • Management & governanceSYP 48M⁦6%⁩
  • Design & permitsSYP 96M⁦12%⁩
  • Civil worksSYP 304.1M⁦37%⁩
  • MEP worksSYP 240.1M⁦29%⁩
  • HandoverSYP 112M⁦14%⁩
  • Unallocated contingencySYP 24.8M⁦3%⁩

Cash flow

Planned, committed, actual and forecast

Spend per period

SYP millions

  • Planned
  • Actual
  • Forecast

Cumulative S-curve

Cumulative to close

  • Actual, then forecast
  • Planned, cumulative
  • Committed, cumulative
  • Forecast

Earned value management

At the data date ⁦2026-10-28⁩

Planned value, earned value and actual cost

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Finish by earned schedule

⁦2030-05-22⁩+1,057

SPI(t) ⁦0.33⁩ against the approved finish ⁦2027-06-30⁩

Planned valuePV
SYP 448.9M
The value of the work that should be done by today.
PV
Earned valueEV
SYP 66M
The value of the work actually done, at plan prices.
EV = % complete × BAC
Actual costAC
SYP 66M
What has actually been spent on the work done.
AC
Budget at completionBAC
SYP 825M
The approved budget for the whole project.
BAC
Cost varianceCV
⁦+0.00⁩ SYP M
Earned less actual; negative means paying more than the value.
CV = EV − AC
Schedule varianceSV
⁦−382.86⁩ SYP M
Earned less planned; negative means behind, in value.
SV = EV − PV
Cost performance indexCPI
1.00
Value produced per pound spent; under 1 is an overrun.
CPI = EV ÷ AC
Schedule performance indexSPI
0.15
Work done over work planned; under 1 is behind.
SPI = EV ÷ PV
Estimate at completionEAC
SYP 825M
What the project will cost when it finishes, as forecast.
EAC = BAC ÷ CPI
Estimate to completeETC
SYP 759M
What is still to be spent to completion.
ETC = EAC − AC
Variance at completionVAC
⁦+0.00⁩ SYP M
Budget less the estimate; negative is an overrun.
VAC = BAC − EAC
To-complete performance indexTCPI
1.00
The cost efficiency the rest must reach to stay on budget.
TCPI = (BAC − EV) ÷ (BAC − AC)

Automatic end-of-project forecast

Four ways to estimate the final cost, and the date earned schedule points to

  • At today’s cost performanceSYP 825M
  • If the rest goes to planSYP 825M
  • At cost and schedule performanceSYP 5.2B
  • The PM’s bottom-up estimateSYP 825M
  • The performance needed on the rest is below what has been achieved; the budget holds.

Estimate at completion at that performance

SYP 825M

Variance at completion: ⁦+0.00⁩ SYP M