Baniyas Pilot Seawater Desalination Plant
Add to watchlistA pilot seawater desalination plant in Baniyas to test the technology and cost before scaling along the coast — paused while its allocation in the investment plan is confirmed.
Budget (BAC)
Actual cost
8% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
123 days behind baseline
PlanningStage 3 of 5
Next gate:Execution24 April 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate3 December 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate1 February 2026Planning · Current stagePlanning · Current stage
- Gate into «Execution»DecisionNot held yetDate24 April 2026Execution · Not startedExecution · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started