PRJ-2026-026On hold3PlanningWaterfallStoppedDelivered by:Ministry of Energy

Baniyas Pilot Seawater Desalination Plant

Add to watchlist

A pilot seawater desalination plant in Baniyas to test the technology and cost before scaling along the coast — paused while its allocation in the investment plan is confirmed.

Budget (BAC)

SYP 825M

Actual cost

SYP 66M

⁦8%⁩ of budget

Progress

⁦8%⁩Awaiting acceptance ⁦6%⁩

Estimate at completion

SYP 825M

SPI · CPI

0.89Schedule performance index · 0.891.00Cost performance index · 1.00

Forecast finish

⁦2027-10-31⁩

123 days behind baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution24 April 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 December 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate1 February 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate24 April 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started