Baniyas Pilot Seawater Desalination Plant Subtask Last item under this branch 2027-10-31 8% Baniyas Pilot Seawater Desalination Plant Planned: 2026-02-01 → 2027-06-30 Forecast: 2026-02-01 → 2027-10-31 Float: 0d
1 Management & governance Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2026-10-26 100% Management & governance Planned: 2026-02-01 → 2026-05-18 Actual: 2026-02-01 → 2026-10-26
1.1 Project plan & baseline Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-07-17 100% Project plan & baseline Planned: 2026-02-01 → 2026-04-07 Actual: 2026-02-01 → 2026-07-17
1.2 Monitoring & reporting Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-10-26 100% Monitoring & reporting Planned: 2026-03-14 → 2026-05-18 Actual: 2026-05-16 → 2026-10-26
Project plan approved Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-10-26 100% Project plan approved Planned: 2026-05-18 → 2026-05-18 Actual: 2026-10-26 → 2026-10-26 Project plan approved
2 Design & permits Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2027-01-16 17% Design & permits Planned: 2026-04-24 → 2026-08-08 Forecast: 2026-04-24 → 2027-01-16 Float: 0d
2.1 Detailed design Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-12-11 33% Detailed design Planned: 2026-04-24 → 2026-06-28 Forecast: 2026-04-24 → 2026-12-11 Float: 0d Drag to change its duration +166
2.2 Permits & approvals Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-01-16 0% Permits & approvals Planned: 2026-06-03 → 2026-08-08 Forecast: 2026-11-19 → 2027-01-16 Float: 0d Drag to change its dates +161
Designs approved Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-01-16 0% Designs approved Planned: 2026-08-08 → 2026-08-08 Forecast: 2027-01-16 → 2027-01-16 Float: 288d Drag to change its dates Designs approved
3 Civil works Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2027-05-04 0% Civil works Planned: 2026-07-14 → 2026-12-08 Forecast: 2026-12-25 → 2027-05-04 Float: 0d
3.1 Site works & excavation Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-02-21 0% Site works & excavation Planned: 2026-07-14 → 2026-09-17 Forecast: 2026-12-25 → 2027-02-21 Float: 0d Drag to change its dates +157
3.2 Structure Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-03-29 0% Structure Planned: 2026-08-24 → 2026-10-28 Forecast: 2027-01-30 → 2027-03-29 Float: 0d Drag to change its dates +152
3.3 Finishes Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-05-04 0% Finishes Planned: 2026-10-04 → 2026-12-08 Forecast: 2027-03-07 → 2027-05-04 Float: 0d Drag to change its dates +147
Build complete Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-05-04 0% Build complete Planned: 2026-12-08 → 2026-12-08 Forecast: 2027-05-04 → 2027-05-04 Float: 180d Drag to change its dates Build complete
4 MEP works Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2027-08-20 0% MEP works Planned: 2026-11-14 → 2027-04-09 Forecast: 2027-04-12 → 2027-08-20 Float: 0d
4.1 Supply Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-06-09 0% Supply Planned: 2026-11-14 → 2027-01-18 Forecast: 2027-04-12 → 2027-06-09 Float: 0d Drag to change its dates +142
4.2 Installation Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-07-15 0% Installation Planned: 2026-12-24 → 2027-02-28 Forecast: 2027-05-18 → 2027-07-15 Float: 0d Drag to change its dates +137
4.3 Testing & commissioning Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-08-20 0% Testing & commissioning Planned: 2027-02-03 → 2027-04-09 Forecast: 2027-06-23 → 2027-08-20 Float: 0d Drag to change its dates +133
Testing & acceptance complete Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-08-20 0% Testing & acceptance complete Planned: 2027-04-09 → 2027-04-09 Forecast: 2027-08-20 → 2027-08-20 Float: 72d Drag to change its dates Testing & acceptance complete
5 Handover Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2027-10-31 0% Handover Planned: 2027-03-16 → 2027-06-30 Forecast: 2027-07-29 → 2027-10-31 Float: 0d
5.1 Provisional acceptance Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-09-25 0% Provisional acceptance Planned: 2027-03-16 → 2027-05-20 Forecast: 2027-07-29 → 2027-09-25 Float: 0d Drag to change its dates +128
5.2 Final acceptance Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-10-31 0% Final acceptance Planned: 2027-04-26 → 2027-06-30 Forecast: 2027-09-03 → 2027-10-31 Float: 0d Drag to change its dates +123
Final handover Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-10-31 0% Final handover Planned: 2027-06-30 → 2027-06-30 Forecast: 2027-10-31 → 2027-10-31 Float: 0d Drag to change its dates Final handover