Programme · PG-09 · Energy & Water Portfolio

Energy & Water Systems Rehabilitation Programme

Off track

The Aleppo substations, the Qalamoun solar field, the As-Suwayda and Madinat al-Salam water networks and the Baniyas pilot plant.

Approved budget
SYP 16.6B

incl. SYP 375M programme reserve

Actual spend
SYP 11.8B

⁦71%⁩ of budget

EAC
SYP 18.2B+11.7%

Estimate at completion

Progress
⁦55%⁩

Planned ⁦61%⁩

Schedule performance index
0.83

Cost performance index 0.90

Manager

Eng. Rami Youssef

Director, Renewable Energy & Environment Projects

Sponsor

Salma Al-Zaim

Deputy President, Finance, Administration & the Investment Plan

Projects

5 projects

2024-01-14 — 2027-10-31

On track 3Critical 1On hold 1

Programme objectives

What the programme must achieve, and the strategic objectives it serves.

  1. 1

    Rehabilitate 55% of the damaged power and water stations in the covered governorates

  2. 2

    15% of added power from renewables

  3. 3

    Cut power rationing hours 12% from baseline

Programme benefits

From baseline to target

  • Stations rehabilitated

    by ⁦2027⁩
    Baseline 38Current 43 %Target 55
  • Renewable energy share

    by ⁦2026⁩
    Baseline 4Current 14.1 %Target 15
  • Generation fuel savings

    by ⁦2027⁩
    Baseline 0Current 240 SYP MTarget 550

Roadmap

One lane per project: start to forecast finish, with the progress earned and the baseline finish.

EarnedRemainingBaseline finishSlip
2024202520262027
2027-02-03
2026-11-12
2027-04-22
2027-09-30
2027-10-31

Dependencies between projects

What waits on what. Red links are on the programme’s critical path.

Critical path

What each project needs from the one before

  • Critical

    The Suwayda water network applies the standard rehabilitation specification approved for the Aleppo stations

  • Lessons from the Madinat al-Salam water network are applied in Suwayda

  • The desalination plant is fed from the Qalamoun solar surplus through the grid

Shared risks

Risks that hit more than one project, managed at programme level.

16

A late Aleppo stations rehab holds up the specification and pushes Suwayda into summer 2027

PRK-09-1·Mitigate·Eng. Rami Youssef

Affects

Open risks in the programme’s projects

5 risks

Open risks in the programme’s projects
  • Critical1
  • High2
  • Medium1
  • Low1
  • Risks 5
Probability
5
4
3
2
1
12345

Impact

Open risks in the programme’s projects
Probability \ Impact12345
50 · Low0 · Medium0 · High0 · Critical1 · Critical
40 · Low0 · Medium0 · Medium1 · High0 · Critical
30 · Low0 · Low0 · Medium1 · Medium1 · High
20 · Low0 · Low1 · Low0 · Medium0 · Medium
10 · Low0 · Low0 · Low0 · Low0 · Low

Programme KPIs · Stakeholders

Stakeholders

Power against interest; click a person to see their role.

Power

Keep satisfied0

Manage closely4

Monitor0

Keep informed0

Salma Al-ZaimManage closelyEng. Rami YoussefManage closelyEng. Maher Al-HamawiManage closelyEng. Wassim Al-AzmManage closely

Interest

Programme decisions

What the committees decided on the programme’s projects, and what the programme raised to them.

Committees

National Projects Steering Committee

Monthly · Quorum ⁦5⁩

Dr. Ziad Al-Atassi · Deputy President, Strategy & PerformanceEng. Abdulrahman Al-Kilani · Deputy President, Development Projects Follow-upEng. Khaled Al-Kayyali · Deputy President, Digital Transformation
Chair: Dr. Samer Al-DaqqarNext meeting 2026-11-03
Authority Executive Council

Weekly · Quorum ⁦4⁩

Dr. Ziad Al-Atassi · Deputy President, Strategy & PerformanceEng. Abdulrahman Al-Kilani · Deputy President, Development Projects Follow-upEng. Khaled Al-Kayyali · Deputy President, Digital TransformationSalma Al-Zaim · Deputy President, Finance, Administration & the Investment Plan
Chair: Dr. Samer Al-DaqqarNext meeting 2026-10-28

Programme projects

The programme’s performance is computed from these projects.

⁦5⁩ results
Export CSV
Manager
Aleppo 230 kV Substations RehabilitationPRJ-2026-004Eng. Maher Al-Hamawi4ExecutionCritical⁦68%⁩SYP10.3BSYP12.3B⁦+19.0%⁩0.74Schedule performance index · 0.740.84Cost performance index · 0.84
20 MW Qalamoun Solar FieldPRJ-2026-010Eng. Rami Youssef4ExecutionOn track⁦58%⁩SYP2.4BSYP2.4B⁦−1.0%⁩1.02Schedule performance index · 1.021.01Cost performance index · 1.01
Suwayda Drinking-Water Network from Al-Ain DamPRJ-2026-025Eng. Rami Youssef4ExecutionOn track⁦36%⁩SYP1.1BSYP1B⁦−2.0%⁩1.03Schedule performance index · 1.031.02Cost performance index · 1.02
Baniyas Pilot Seawater Desalination PlantPRJ-2026-026Eng. Rami Youssef3PlanningOn hold⁦8%⁩SYP825MSYP825M⁦0.0%⁩0.89Schedule performance index · 0.891.00Cost performance index · 1.00
Madinat al-Salam Drinking-Water Network (Quneitra)PRJ-2026-036Eng. Maher Al-Hamawi5ClosureOn track⁦97%⁩SYP1.7BSYP1.7B⁦−1.0%⁩0.98Schedule performance index · 0.981.01Cost performance index · 1.01
Total · 5SYP16.3BSYP18.2B
⁦1⁩–⁦5⁩ of ⁦5⁩

Budget shares

Budget shares

SYP 16.3B

Budget

  • Aleppo 230 kV Substations RehabilitationSYP 10.3B⁦63%⁩
  • 20 MW Qalamoun Solar FieldSYP 2.4B⁦15%⁩
  • Suwayda Drinking-Water Network from Al-Ain DamSYP 1.1B⁦6%⁩
  • Baniyas Pilot Seawater Desalination PlantSYP 825M⁦5%⁩
  • Madinat al-Salam Drinking-Water Network (Quneitra)SYP 1.7B⁦10%⁩
Budget shares
CategoryValueShare
Aleppo 230 kV Substations RehabilitationSYP 10.3B⁦63%⁩
20 MW Qalamoun Solar FieldSYP 2.4B⁦15%⁩
Suwayda Drinking-Water Network from Al-Ain DamSYP 1.1B⁦6%⁩
Baniyas Pilot Seawater Desalination PlantSYP 825M⁦5%⁩
Madinat al-Salam Drinking-Water Network (Quneitra)SYP 1.7B⁦10%⁩
TotalSYP 16.3B⁦100%⁩