A late Aleppo stations rehab holds up the specification and pushes Suwayda into summer 2027
PRK-09-1·Mitigate·Eng. Rami Youssef
Programme · PG-09 · Energy & Water Portfolio
The Aleppo substations, the Qalamoun solar field, the As-Suwayda and Madinat al-Salam water networks and the Baniyas pilot plant.
incl. SYP 375M programme reserve
71% of budget
Estimate at completion
Planned 61%
Cost performance index 0.90
Manager
Eng. Rami Youssef
Director, Renewable Energy & Environment Projects
Sponsor
Salma Al-Zaim
Deputy President, Finance, Administration & the Investment Plan
Projects
5 projects
2024-01-14 — 2027-10-31
On track 3Critical 1On hold 1
What the programme must achieve, and the strategic objectives it serves.
Rehabilitate 55% of the damaged power and water stations in the covered governorates
15% of added power from renewables
Cut power rationing hours 12% from baseline
From baseline to target
Stations rehabilitated
by 2027Renewable energy share
by 2026Generation fuel savings
by 2027One lane per project: start to forecast finish, with the progress earned and the baseline finish.
What waits on what. Red links are on the programme’s critical path.
Critical path
Critical
The Suwayda water network applies the standard rehabilitation specification approved for the Aleppo stations
Lessons from the Madinat al-Salam water network are applied in Suwayda
The desalination plant is fed from the Qalamoun solar surplus through the grid
Risks that hit more than one project, managed at programme level.
A late Aleppo stations rehab holds up the specification and pushes Suwayda into summer 2027
PRK-09-1·Mitigate·Eng. Rami Youssef
5 risks
Impact
| Probability \ Impact | 1 | 2 | 3 | 4 | 5 |
|---|---|---|---|---|---|
| 5 | 0 · Low | 0 · Medium | 0 · High | 0 · Critical | 1 · Critical |
| 4 | 0 · Low | 0 · Medium | 0 · Medium | 1 · High | 0 · Critical |
| 3 | 0 · Low | 0 · Low | 0 · Medium | 1 · Medium | 1 · High |
| 2 | 0 · Low | 0 · Low | 1 · Low | 0 · Medium | 0 · Medium |
| 1 | 0 · Low | 0 · Low | 0 · Low | 0 · Low | 0 · Low |
Population served by rehabilitated water networks
76.4%
+1
Target 78.0%98%
Infrastructure projects delivered to plan
73%
+1
Target 85%86%
Citizen satisfaction at governorate service centres
71%
+1
Target 72%99%
Public facilities rehabilitated this year (cumulative)
48facilities
+4
Target 6080%
Power against interest; click a person to see their role.
Keep satisfied0
Manage closely4
Monitor0
Keep informed0
Interest
What the committees decided on the programme’s projects, and what the programme raised to them.
Baniyas pilot plant suspended until the allocation is confirmed
Authority Executive Council · 2026-10-06 · DEC-2026-035
Mid-execution review passed for the Qalamoun solar field
Project Approval Committee · 2026-09-30 · DEC-2026-034
Task force formed for the Aleppo substations contractor’s distress
Authority Executive Council · 2026-09-22 · DEC-2026-032
Committees
Monthly · Quorum 5
Members
6 members
Weekly · Quorum 4
The programme’s performance is computed from these projects.
Display options
| Manager | ||||||||
|---|---|---|---|---|---|---|---|---|
| Aleppo 230 kV Substations RehabilitationPRJ-2026-004 | Eng. Maher Al-Hamawi | 4Execution | Critical | 68% | SYP10.3B | SYP12.3B+19.0% | 0.74Schedule performance index · 0.74 | 0.84Cost performance index · 0.84 |
| 20 MW Qalamoun Solar FieldPRJ-2026-010 | Eng. Rami Youssef | 4Execution | On track | 58% | SYP2.4B | SYP2.4B−1.0% | 1.02Schedule performance index · 1.02 | 1.01Cost performance index · 1.01 |
| Suwayda Drinking-Water Network from Al-Ain DamPRJ-2026-025 | Eng. Rami Youssef | 4Execution | On track | 36% | SYP1.1B | SYP1B−2.0% | 1.03Schedule performance index · 1.03 | 1.02Cost performance index · 1.02 |
| Baniyas Pilot Seawater Desalination PlantPRJ-2026-026 | Eng. Rami Youssef | 3Planning | On hold | 8% | SYP825M | SYP825M0.0% | 0.89Schedule performance index · 0.89 | 1.00Cost performance index · 1.00 |
| Madinat al-Salam Drinking-Water Network (Quneitra)PRJ-2026-036 | Eng. Maher Al-Hamawi | 5Closure | On track | 97% | SYP1.7B | SYP1.7B−1.0% | 0.98Schedule performance index · 0.98 | 1.01Cost performance index · 1.01 |
| Total · 5 | SYP16.3B | SYP18.2B |
SYP 16.3B
Budget
| Category | Value | Share |
|---|---|---|
| Aleppo 230 kV Substations Rehabilitation | SYP 10.3B | 63% |
| 20 MW Qalamoun Solar Field | SYP 2.4B | 15% |
| Suwayda Drinking-Water Network from Al-Ain Dam | SYP 1.1B | 6% |
| Baniyas Pilot Seawater Desalination Plant | SYP 825M | 5% |
| Madinat al-Salam Drinking-Water Network (Quneitra) | SYP 1.7B | 10% |
| Total | SYP 16.3B | 100% |