RSK-0043Baniyas Pilot Seawater Desalination Plant
Allocation left out of the 2027 investment plan; tender stays on hold
A risk's detail, response, contingency and residual risk.
Latest escalation · ESC-2026-012
Executive Council
The Baniyas pilot plant allocation is missing from the draft 2027 investment plan and the tender stays suspended
FundingSYP 120M· Asked from: Authority Executive Council
Put SYP 120M into the 2027 investment plan, or approve a funding model with the Syrian Development Fund
Risk statement
From cause to event to impact — with the preventive controls before the event and the contingency after it
Cause
The project is not in the draft 2027 investment plan; power and replacement-housing projects took priority
Preventive controls
- Present a funding model with the Syrian Development Fund
1 / 1
Event
Allocation left out of the 2027 investment plan; tender stays on hold
The 2027 investment plan approved without the project
Contingency
Run a reduced-capacity pilot phase from the maintenance allocations
Impact
The tender stays suspended and Baniyas waits for extra drinking water, with about SYP 120M a year spent on tanker supply
Assessment
The level before and after the response
Inherent
Residual
Exposure
SYP 120M
Residual
44% off the score
Score trend
Last six months
- Score
- Target residual
Escalation path
Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the PMO director
Last reviewed 20 days ago
Project manager
Eng. Rami Youssef
Currently followed up hereProgramme manager
Eng. Rami Youssef
Automatically at 15 days unreviewed · threshold passed 5 days agoPMO director
Current levelDr. Reem Al-Qabbani
Automatically at 20 days unreviewed · threshold passed 0 days ago- 4
Executive Council
Dr. Samer Al-Daqqar
By the PMO director’s decision
Mitigation plan
Each action with its owner and date — tick it off when complete
Present a funding model with the Syrian Development Fund
Eng. Rami YoussefEng. Rami YoussefDirector, Renewable Energy & Environment ProjectsP-028rami.youssef@psa.gov.syIn progressIn 23 days2026-11-20
Trigger
The 2027 investment plan approved without the project
Contingency
Run a reduced-capacity pilot phase from the maintenance allocations