Execution
Suspension, resumption & cancellation
The decision, the rationale and the approvals
- Form no.
- PSA-PMO-F10
- Template edition
- 1.0
- Version
- V1
- Form date
- 2026-09-21
Auto-filled — Filled by the platform from the project record, not typed.
- Project code
- PRJ-2026-026
- Project
- Baniyas Pilot Seawater Desalination Plant
- Portfolio
- Energy & Water Portfolio
- Sector
- Development Projects Follow-up Sector
- Sponsor
- Salma Al-Zaim
- Project manager
- Eng. Rami Youssef
1The decision asked for
- Action
- Suspension
- Status nowAuto-filled
- Active
- Status afterAuto-filled
- Suspended
- Requested onAuto-filled
- 2026-09-21
- Planned resumption
- 2027-01-15
- Length of the suspensionAuto-filled
- 116 days
2Rationale
Waiting for 2027 funding of the performance contracts with the energy service companies.
3Effect on the projectAuto-filled
Approved budget
SYP 825M
Committed
SYP 77.5M
Actual
SYP 66M
Progress
8%
A suspended project keeps its stage and resumes in it; its progress is frozen in the portfolio’s progress while suspended.
Approval logChain: Suspension, resumption & cancellation · version 1
Every decision on the form — who, their role, the note and the time. It prints with the form.
| # | Step | Kind | Name | Decision | Note | Date & time |
|---|---|---|---|---|---|---|
| 1 | Author | — | Eng. Rami YoussefDirector, Renewable Energy & Environment Projects | Submitted | — | 2026-09-21 11:38 |
| 2 | PMO opinion | Methodology review | Dr. Reem Al-QabbaniPMO — director | Approved | — | 2026-09-22 09:06 |
| 3 | Effect on financial commitments | Financial approval | Rasha Al-MudarresFinance | Approved | — | 2026-09-23 13:28 |
| 4 | Project Approval Committee | Technical acceptance | Dr. Reem Al-QabbaniProject Approval Committee | Approved | — | 2026-09-24 12:00 |
| 5 | Sponsor’s decision | Technical acceptance | Salma Al-ZaimProject sponsor | Approved | — | 2026-09-24 12:27 |
Signatures
PMO opinion
Dr. Reem Al-Qabbani
Approved2026-09-22
Effect on financial commitments
Rasha Al-Mudarres
Approved2026-09-23
Sponsor’s decision
Salma Al-Zaim
Approved2026-09-24
Project Approval Committee
Dr. Reem Al-Qabbani
Approved2026-09-24