PMO dashboardPlanning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORMCommand center

Live· Updated just now

Executive monitoring centre

The enterprise portfolio as it moves: strategy, major projects, risks, budget and decisions.

--:--:--

Wednesday

28 October 2026

Projects

36

⁦18⁩ on track · ⁦6⁩ delayed or critical

Progress

⁦52%⁩

Planned ⁦57%⁩

Spent to date

SYP 60.3B

of SYP 129.3B (⁦47%⁩)

Estimate at completion

SYP 139.5B

Forecast overrun SYP 10.2B

Performance indices

0.85SPI0.93CPI

Needs attention

18high risks9decisions

Open high risks · decisions and gates waiting

Strategy

Selected KPIs

  • Infrastructure projects delivered to plan73%
  • Ministry systems hosted on the government cloud47%
  • Grain reception centres rehabilitated84%
  • Approved investment plan executed77%

Project map

Pick a governorate or a project
Al-Hasakah · 1Aleppo · 2Raqqa · 1As-Suwayda · 1Daraa · 1Deir ez-Zor · 2Hama · 1Homs · 2Idlib · 1Latakia · 1Quneitra · 1Rif Dimashq · 3Tartus · 1Damascus city · 18Rukn al-DinMuhajirinMezzehBarzehSaroujaOld DamascusQanawatMidanDummarQadamKafr SousaSalhiyehBoundaries: OCHA / HDX (CC BY-IGO)Darayya Replacement Housing
  • On track18
  • At risk10
  • Off track4
  • Critical2
  • On hold2

Major projects

Off trackPRJ-2026-002

Darayya Replacement Housing

Replacement housing for families returning to Darayya — four linked residential blocks with water, power and internal roads, a school and a health centre, on land allocated by Rif Dimashq Governorate.

Progress⁦42%⁩

⁦42%⁩
Budget
SYP 29.5B
EAC
SYP 31.7B
Forecast slip
⁦74⁩ days
Governorate
Rif Dimashq
SPI0.82Schedule performance index · 0.82CPI0.93Cost performance index · 0.93⁦88%⁩ chance of slipping within ⁦60⁩ days
Open the project workspace

Off track

Critical risks

18
  • 25Main contractor cash-flow trouble and late payment of subcontractorsAleppo 230 kV Substations RehabilitationSYP 900M
  • 20Steel and concrete price rises driving price-adjustment claimsDarayya Replacement HousingSYP 1.2B
  • 20Contractor’s financial claims piling up over unapproved change ordersHama National Hospital Upgrade & ExtensionSYP 1B
  • 20Late hand-over of the northern plot and utility diversions in blocks 3 and 4Darayya Replacement HousingSYP 775M
  • 20Unforeseen ground conditions and groundwater at the foundations of axes 12 to 16Douma Wastewater Treatment PlantSYP 675M

Budget by portfolio

  • Digital Government Services & Data PortfolioSYP 5.1B

  • Health, Education & Industrial Recovery PortfolioSYP 36.8B

  • Government Digital Infrastructure & Systems PortfolioSYP 9.4B

  • Energy & Water PortfolioSYP 18.2B

  • Reconstruction & Infrastructure PortfolioSYP 69.3B

  • Planning, Statistics & Capability PortfolioSYP 762.3M

  • Bar: spent · tick: budget · figure: EAC

Decisions needed

9
  • ⁦26⁩ h lateApprove the October National Steering Committee minutes
  • ⁦22⁩ h leftPay subcontractors directly on the Aleppo 230 kV substations rehabilitation
  • ⁦50⁩ h leftRefer the Hama National Hospital contractor’s claims to arbitration
  • ⁦96⁩ h leftApprove the updated corrective plan for the Unified Government e-Services Platform
  • ⁦140⁩ h leftRelease SYP 550M of the Reconstruction & Infrastructure portfolio reserve to speed up the Darayya housing land hand-over
Decide on the executive dashboard
LIVE
  1. 10:42New escalation: five foundation axes to redesign — the Douma wastewater treatment plant
  2. 10:15Certificate 27 approved on the Darayya replacement housing — SYP 790M
  3. 09:5014 MW of panels now installed at the Qalamoun solar field
  4. 09:20Civil registry / interoperability integration risk raised to 16
  5. 08:40Citizen satisfaction with digital government services updated: 74% (+2 pts)