Development Strategic Framework 2026–2030 and the 2026–2028 Medium-Term Plan
Develop rural areas and spur agricultural investment
Rehabilitated grain reception centres and irrigation networks, and investment agreements in farming and food industries.
Attainment
of the 90% target
Attainment through 2026
Weight in theme
45%
Food Security & Rural Development
KPI status
2
- On track1
- At risk1
- Off track0
Linked budget
SYP 0
0 projects
Why this objective
The countryside carries Syria’s food security: working grain reception centres, passable farm roads and investment in food industries keep farmers on their land.
Directions it delivers
Values it carries
- Partnership
Attainment through 2026
The objective’s monthly attainment against this year’s target.
| Period | Attainment |
|---|---|
| Jan | 73.1% |
| Feb | 74.7% |
| Mar | 76.3% |
| Apr | 78.6% |
| May | 79.3% |
| Jun | 81.6% |
| Jul | 82.5% |
| Aug | 85.1% |
| Sep | 86.5% |
| Oct | 88.0% |
KPIs
Baseline, target and actual for each KPI, and progress from baseline to target.
- Grain reception centres rehabilitated
K-4.2.1Monthly%
Baseline
76
Target
88
Actual
84
67% - Agricultural investment agreements signed
K-4.2.2Quarterlyagreements
Baseline
0
Target
6
Actual
4
67%
Sub-objectives
Their weights inside the objective and their progress; the weighted sum is the objective’s attainment.
Rehabilitate grain reception centres and farm roads
OBJ-08.1
87%Eng. Bashir Al-TaiEng. Bashir Al-TaiDeputy President, Local Development & GovernoratesP-049bashir.altai@psa.gov.syWeight
50%
Agricultural and food-industry investment agreements
OBJ-08.2
89%Jwan OthmanJwan OthmanDirector, Partnerships & Development FinanceP-051jwan.othman@psa.gov.syWeight
50%
Contributing initiatives & projects
The objective’s approved initiatives and their projects, and each project’s share of the contribution by budget.
Approval & change log
This item’s definition as approved in the plan version in force, and every change request on it with the old and proposed values and the decision.
No change requests on this item since the plan was approved.
Corrective actions
What we are doing to bring the KPI back on track, who owns it, and by when.
Finish the four late grain reception centres in Hasakah before the next season plan
Eng. Bashir Al-TaiEng. Bashir Al-TaiDeputy President, Local Development & GovernoratesP-049bashir.altai@psa.gov.syDue 2026-11-15In 18 days2026-11-15K-4.2.1Hasakah Wheat Digital Crop SurveyIn progress
Challenges & notes
What holds the objective back and what leadership should know.
- Note
Six grain reception centres in Deir ez-Zor and Raqqa were handed over before harvest, and two food-industry investment agreements were signed in Hama.
Eng. Bashir Al-Tai · 2026-10-16