Off trackAutomaticIntegrated Public Financial Management System — Phase 1PRJ-2026-001Remove from watchlistProgress61%SPI0.8261%Schedule variance17.6%Forecast slip58 daysHealth score61 My noteAdd a note to yourself…CompareOpen project
Off trackCorrective plan requiredAutomaticDarayya Replacement HousingPRJ-2026-002Remove from watchlistProgress42%SPI0.8242%Schedule variance17.6%Forecast slip74 daysHealth score53 My noteTie the reserve release to handing over blocks 3 and 4 of the site.CompareOpen project
CriticalAutomaticAleppo 230 kV Substations RehabilitationPRJ-2026-004Remove from watchlistProgress68%SPI0.7468%Schedule variance26.1%Forecast slip126 daysHealth score30 My noteNo more delays on subcontractor dues from today.CompareOpen project
Off trackCorrective plan requiredAutomaticSheikh Najjar Industrial City RehabilitationPRJ-2026-006Remove from watchlistProgress39%SPI0.7839%Schedule variance22.0%Forecast slip95 daysHealth score63 My noteAdd a note to yourself…CompareOpen project
CriticalAutomaticHama National Hospital Upgrade & ExtensionPRJ-2026-007Remove from watchlistProgress57%SPI0.7057%Schedule variance30.5%Forecast slip152 daysHealth score30 My noteTrack the arbitration route with Legal before the committee.CompareOpen project
At riskAutomaticUnified Government e-Services PlatformPRJ-2026-014Remove from watchlistProgress58%SPI0.8758%Schedule variance13.4%Forecast slip42 daysHealth score72 My noteWeekly update on the civil registry / interoperability integration until launch.CompareOpen project
Off trackAutomaticDouma Wastewater Treatment PlantPRJ-2026-020Remove from watchlistProgress44%SPI0.8044%Schedule variance20.0%Forecast slip64 daysHealth score68 My noteAdd a note to yourself…CompareOpen project