Hama National Hospital contractor claims; Digital Government Services & Data portfolio progress.

Held on

13 October 2026

10:00 – 12:05

  1. Held
  2. Minutes written
  3. Published
  4. Approved
Quorum met · ⁦6⁩ present, ⁦5⁩ neededAwaiting Dr. Samer Al-Daqqar’s approval

Agenda

⁦105⁩ of ⁦120⁩ min

  1. Approve the previous minutes

    ApprovalDr. Reem Al-Qabbani

    ⁦5⁩ min

  2. Hama National Hospital — contractor claims

    DecisionEng. Sara Al-Barazi

    ⁦50⁩ min

  3. Digital Government Services & Data portfolio progress

    DiscussionBasel Al-Mahayni

    ⁦40⁩ min

  4. Any other business

    DiscussionDr. Samer Al-Daqqar

    ⁦10⁩ min

Minutes

  1. 1. Approve the previous minutes

    September minutes approved.

  2. 2. Hama National Hospital — contractor claims

    PRJ-2026-007

    Claims total SYP 1.85bn and 150 days. Referred to the contract’s dispute board; the hospitals project manager prepares the file.

  3. 3. Digital Government Services & Data portfolio progress

    PF-DT

    The committee wants a portfolio brief in November focused on the risk in integrating with the civil registry and the ministries.

  4. 4. Any other business

    No minutes were written for this item.

Decisions & votes

Voting rule: Two-thirds of those present for baseline decisions, simple majority otherwise

  • Hama National Hospital contractor’s claims referred to the dispute committee

    DEC-2026-037Approved

    For ⁦6⁩Against ⁦0⁩Abstain ⁦0⁩Carried

    • Dr. Samer Al-Daqqar · For
    • Dr. Ziad Al-Atassi · For
    • Eng. Abdulrahman Al-Kilani · For
    • Eng. Khaled Al-Kayyali · Did not vote
    • Salma Al-Zaim · For
    • Rasha Al-Mudarres · For
    • Dr. Reem Al-Qabbani · For

Tasks

They show in the task register and on the owner’s calendar

Attendance & quorum

Quorum: Five of seven voting members, including the chair or vice-chair

Quorum met6 / 7

At least ⁦5⁩ voting members needed

  • Dr. Samer Al-DaqqarDr. Samer Al-DaqqarPresident, Planning and Statistics AuthorityChairP-001samer.aldaqqar@psa.gov.syPresent
  • Dr. Ziad Al-AtassiDr. Ziad Al-AtassiDeputy President, Strategy & PerformanceVice-chairP-009ziad.alatassi@psa.gov.syPresent
  • Eng. Abdulrahman Al-KilaniEng. Abdulrahman Al-KilaniDeputy President, Development Projects Follow-upMemberP-010abdulrahman.alkilani@psa.gov.syPresent
  • Eng. Khaled Al-KayyaliEng. Khaled Al-KayyaliDeputy President, Digital TransformationMemberP-011khaled.alkayyali@psa.gov.syRemote
  • Dr. Reem Al-QabbaniDr. Reem Al-QabbaniDirector, National Project Management OfficeSecretaryP-002reem.alqabbani@psa.gov.syPresent
  • Rasha Al-MudarresRasha Al-MudarresDirector General, Finance & ContractsMemberP-018rasha.almudarres@psa.gov.syPresent
  • Eng. Sara Al-BaraziEng. Sara Al-BaraziSenior Project Manager — Hospitals & Health FacilitiesGuestP-022sara.albarazi@psa.gov.syPresent
  • Basel Al-MahayniBasel Al-MahayniDirector General, Digital Government Services & Portfolio Manager, Digital Government Services & DataObserverP-003basel.almahayni@psa.gov.syPresent

Attachments

⁦2⁩ files

  • Hama-hospital-claims-summary.pdfEng. Sara Al-Barazi · ⁦3.8⁩ MB
  • Digital-portfolio-October.pptxBasel Al-Mahayni · ⁦5.0⁩ MB

Smart minutes summaryAI-generated

Drafted by the assistant from the agenda, the minutes, the decisions and the tasks. Review it before approval.

Shown only to invitees and the PMO, and leaves out what your permissions do not let you see.

Meeting pack

Built automatically from the projects on the agenda: a card per project, the decisions needed, the support requested and the overdue tasks.

Project cards 1

Decisions needed

4

Support requested

2
  • ISS-0109 · Hama National Hospital Upgrade & Extension

    A decision· Asked from: Authority Executive Council

    A decision to accept an equivalent finishing material on the consultant’s advice, or to extend the supply period

  • CP-2026-03 · Hama National Hospital Upgrade & Extension

    A decision· Asked from: Authority Executive Council

    A decision to accept an equivalent finishing material on the consultant’s advice