PRJ-2026-007 · From item 2
Hama National Hospital Upgrade & ExtensionPlanned to date 82%
- SPI
- 0.70
- Forecast finish
- 2027-06-01
- Budget
- SYP 16B
152 days lateMaterial risks: 3Open impediments: 4Corrective plan CP-2026-03
Hama National Hospital contractor claims; Digital Government Services & Data portfolio progress.
Held on
13 October 202610:00 – 12:05
105 of 120 min
Approve the previous minutes
ApprovalDr. Reem Al-Qabbani
5 min
Hama National Hospital — contractor claims
DecisionEng. Sara Al-Barazi
50 min
Digital Government Services & Data portfolio progress
DiscussionBasel Al-Mahayni
40 min
Any other business
DiscussionDr. Samer Al-Daqqar
10 min
1. Approve the previous minutes
September minutes approved.
2. Hama National Hospital — contractor claims
PRJ-2026-007Claims total SYP 1.85bn and 150 days. Referred to the contract’s dispute board; the hospitals project manager prepares the file.
3. Digital Government Services & Data portfolio progress
PF-DTThe committee wants a portfolio brief in November focused on the risk in integrating with the civil registry and the ministries.
4. Any other business
No minutes were written for this item.
Voting rule: Two-thirds of those present for baseline decisions, simple majority otherwise
Hama National Hospital contractor’s claims referred to the dispute committee
DEC-2026-037Approved
For 6Against 0Abstain 0Carried
They show in the task register and on the owner’s calendar
ACT-0323Basel Al-Mahayni
Quorum: Five of seven voting members, including the chair or vice-chair
At least 5 voting members needed
2 files
Drafted by the assistant from the agenda, the minutes, the decisions and the tasks. Review it before approval.
Shown only to invitees and the PMO, and leaves out what your permissions do not let you see.
Built automatically from the projects on the agenda: a card per project, the decisions needed, the support requested and the overdue tasks.
PRJ-2026-007 · From item 2
Hama National Hospital Upgrade & ExtensionPlanned to date 82%
152 days lateMaterial risks: 3Open impediments: 4Corrective plan CP-2026-03
Agenda item needing a decision · PRJ-2026-007
Hama National Hospital — contractor claimsFrom item 2
Change request awaiting decision · CR-2026-005
Change order 7: medical gases and HVAC redesignHama National Hospital Upgrade & Extension
Change request awaiting decision · CR-2026-006
Extend the contract by 150 daysHama National Hospital Upgrade & Extension
Corrective plan awaiting approval · CP-2026-03
Hama National Hospital Upgrade & ExtensionISS-0109 · Hama National Hospital Upgrade & Extension
A decision· Asked from: Authority Executive Council
A decision to accept an equivalent finishing material on the consultant’s advice, or to extend the supply period
CP-2026-03 · Hama National Hospital Upgrade & Extension
A decision· Asked from: Authority Executive Council
A decision to accept an equivalent finishing material on the consultant’s advice
ACT-0311 · Eng. Wael Al-Khawlani