Original
Original baseline
- Finish
- 2026-09-30
- Budget
- SYP 9.8B
- 17 activities
Approved with the project plan at the planning gate.
Approved 2024-01-14 · by Salma Al-Zaim
Rehabilitating four 230 kV substations in Aleppo city (28 high-voltage bays) and linking them to the control centre, to lengthen supply hours in the neighbourhoods and the industrial zone.
Budget (BAC)
Actual cost
81% of budget
Progress
Estimate at completion
+SYP 2B
SPI · CPI
Forecast finish
126 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure13 July 2026
The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.
Original
Approved with the project plan at the planning gate.
Approved 2024-01-14 · by Salma Al-Zaim
Working
Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.
Created 2026-10-28 · by Eng. Maher Al-Hamawi
What changed from version A to version B
Finish
2026-09-302027-03-08
+159 days
Budget
SYP 9.8BSYP 10.3B
+535.00 SYP M
Milestones moved
5 / 5
Each line starts at the milestone’s date in A and ends at its date in B
Version AVersion B
Difference in SYP millions from A to B
Every saved version with its reason and reference