PRJ-2026-004Critical4ExecutionConstructionStalledDelivered by:Ministry of Energy

Aleppo 230 kV Substations Rehabilitation

Remove from watchlist

Rehabilitating four 230 kV substations in Aleppo city (28 high-voltage bays) and linking them to the control centre, to lengthen supply hours in the neighbourhoods and the industrial zone.

Early warning: ⁦95%⁩ chance of slipping within ⁦30⁩ days

Budget (BAC)

SYP 10.3B

Actual cost

SYP 8.3B

⁦81%⁩ of budget

Progress

⁦68%⁩Awaiting acceptance ⁦9%⁩

Estimate at completion

SYP 12.3B

+SYP 2B

SPI · CPI

0.74Schedule performance index · 0.740.84Cost performance index · 0.84

Forecast finish

⁦2027-02-03⁩

126 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure13 July 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate15 November 2023Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate14 January 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate20 June 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate13 July 2026Closure · Not startedClosure · Not started

Baselines

The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.

  1. Original

    Original baseline

    v1.0Approved & lockedVersion A
    Finish
    ⁦2026-09-30⁩
    Budget
    SYP 9.8B
    ⁦17⁩ activities

    Approved with the project plan at the planning gate.

    Approved ⁦2024-01-14⁩ · by Salma Al-Zaim

  2. Working

    Working baseline

    v2.0-draftWorking draftVersion B
    Finish
    ⁦2027-03-08⁩
    ⁦+159⁩ days
    Budget
    SYP 10.3B
    ⁦17⁩ activities

    Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.

    Created ⁦2026-10-28⁩ · by Eng. Maher Al-Hamawi

    Edit in the schedule

Compare two versions

What changed from version A to version B

Finish

⁦2026-09-30⁩⁦2027-03-08⁩

⁦+159⁩ days

Budget

SYP 9.8BSYP 10.3B

⁦+535.00⁩ SYP M

Milestones moved

5 / 5

Milestones: A to B

Each line starts at the milestone’s date in A and ends at its date in B

2025-012025-072026-012026-072027-01
  • Project plan approved⁦+104⁩
  • Designs approved⁦+183⁩
  • Build complete⁦+302⁩
  • Testing & acceptance complete⁦+296⁩
  • Final handover⁦+159⁩

Version AVersion B

Cost by WBS element

Difference in SYP millions from A to B

  • 1Management & governance⁦+136.25⁩
  • 2Design & permits⁦+272.51⁩
  • 3Civil works⁦+1,068.94⁩
  • 4MEP works⁦+440.71⁩
  • 5Handover⁦+403.99⁩

Version history

Every saved version with its reason and reference

  1. Working baselinev2.0-draftWorking draftFollows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.⁦2026-10-28⁩by Eng. Maher Al-Hamawi
  2. Original baselinev1.0Approved & lockedApproved with the project plan at the planning gate.⁦2024-01-14⁩by Salma Al-Zaim