PRJ-2026-004Critical4ExecutionConstructionStalledDelivered by:Ministry of Energy

Aleppo 230 kV Substations Rehabilitation

Remove from watchlist

Rehabilitating four 230 kV substations in Aleppo city (28 high-voltage bays) and linking them to the control centre, to lengthen supply hours in the neighbourhoods and the industrial zone.

Early warning: ⁦95%⁩ chance of slipping within ⁦30⁩ days

Budget (BAC)

SYP 10.3B

Actual cost

SYP 8.3B

⁦81%⁩ of budget

Progress

⁦68%⁩Awaiting acceptance ⁦9%⁩

Estimate at completion

SYP 12.3B

+SYP 2B

SPI · CPI

0.74Schedule performance index · 0.740.84Cost performance index · 0.84

Forecast finish

⁦2027-02-03⁩

126 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure13 July 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate15 November 2023Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate14 January 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate20 June 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate13 July 2026Closure · Not startedClosure · Not started

Team & roles

4 members, about ⁦2.1⁩ full-time equivalents

Leadership

2 members

  • Eng. Maher Al-HamawiProject manager⁦70%⁩Allocated ⁦130%⁩ across all projectsA
  • Eng. Abdulrahman Al-KilaniFollow-up lead — substations’ readiness to energise⁦20%⁩Allocated ⁦110%⁩ across all projectsR

Specialists

1 member

  • Huda Al-DandalFinancial analyst⁦15%⁩C

Vendor team & advisers

1 member

    A AccountableR ResponsibleC ConsultedI Informed

    Stakeholders

    ⁦6⁩ stakeholders, ⁦4⁩ of them below the engagement needed

    Power / interest matrix

    Pick one to see how they are handled

    Power & influence

    Keep satisfied1

    high power, lower interest

    Manage closely4

    high power and interest

    Monitor0

    minimal effort

    Keep informed1

    high interest, lower power

    Salma Al-ZaimManage closelyEng. Wassim Al-AzmManage closelyProject Management Office (PMO)Manage closelyEnd beneficiariesKeep informedGeneral Directorate of Financial AffairsKeep satisfiedAl-Shahbaa Construction & Rehabilitation Co.Manage closely

    Interest

    Project sponsor

    Salma Al-Zaim

    Decisions and funding

    Influence

    Interest

    Engagement level

    Unaware

    Resistant

    Neutral

    Now

    Supportive

    Target

    Leading

    A gap of ⁦1⁩ step — needs an engagement plan.

    Impact on the project
    Approves gates and changes
    Engagement plan
    Monthly briefing
    Last contact⁦2026-10-15⁩
    ⁦6⁩ results
    Export CSV
    OrganisationRoleActions
    Salma Al-ZaimProject sponsorDecisions and fundingSupportiveLeadingEng. Maher Al-HamawiEng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsP-021maher.alhamawi@psa.gov.sy⁦2026-10-15⁩
    Eng. Wassim Al-AzmProject ownerAccepts deliverables, owns benefitsLeadingEng. Maher Al-HamawiEng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsP-021maher.alhamawi@psa.gov.sy⁦2026-10-18⁩
    Project Management Office (PMO)GovernanceCompliance and data qualitySupportiveEng. Maher Al-HamawiEng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsP-021maher.alhamawi@psa.gov.sy⁦2026-10-12⁩
    General Directorate of Financial AffairsInternal departmentPayment approvalNeutralSupportiveHuda Al-DandalHuda Al-DandalSenior Financial Analyst — Investment PlanP-037huda.aldandal@psa.gov.sy⁦2026-10-09⁩
    Al-Shahbaa Construction & Rehabilitation Co.Main vendorDelivers the contracted workResistantSupportiveEng. Maher Al-HamawiEng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsP-021maher.alhamawi@psa.gov.sy⁦2026-10-19⁩
    End beneficiariesBeneficiariesUsers of the outcomeNeutralSupportiveEng. Maher Al-HamawiEng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsP-021maher.alhamawi@psa.gov.sy⁦2026-09-21⁩
    ⁦1⁩–⁦6⁩ of ⁦6⁩

    Communication plan

    Who needs what, when, through which channel, and who owns it.

    • Project sponsorStatus and decisions neededMonthlyMeetingEng. Maher Al-Hamawi⁦2026-11-10⁩
    • Project ownerDeliverable status and acceptance datesFortnightlyEmailEng. Maher Al-Hamawi⁦2026-10-29⁩
    • PMOData and indicator updatesWeeklyDashboardEng. Maher Al-Hamawi⁦2026-10-26⁩
    • BeneficiariesWhat changes and whenAt milestonesNewsletterEng. Maher Al-HamawiAt launch

    Coming up

    By date

    1. 262026-10PMODashboard · Weekly
    2. 292026-10Project ownerEmail · Fortnightly