PRJ-2026-004Critical4ExecutionConstructionStalledDelivered by:Ministry of Energy

Aleppo 230 kV Substations Rehabilitation

Remove from watchlist

Rehabilitating four 230 kV substations in Aleppo city (28 high-voltage bays) and linking them to the control centre, to lengthen supply hours in the neighbourhoods and the industrial zone.

Early warning: ⁦95%⁩ chance of slipping within ⁦30⁩ days

Budget (BAC)

SYP 10.3B

Actual cost

SYP 8.3B

⁦81%⁩ of budget

Progress

⁦68%⁩Awaiting acceptance ⁦9%⁩

Estimate at completion

SYP 12.3B

+SYP 2B

SPI · CPI

0.74Schedule performance index · 0.740.84Cost performance index · 0.84

Forecast finish

⁦2027-02-03⁩

126 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure13 July 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate15 November 2023Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate14 January 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate20 June 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate13 July 2026Closure · Not startedClosure · Not started
Fields required by the project’s stage (Execution): 15 fields required now.Field settings

Planning and Statistics Authority

Project charter

Aleppo 230 kV Substations Rehabilitation

APPROVEDV2Approved ⁦2024-01-12⁩

1Project identity

Required at this stage
Project name
Aleppo 230 kV Substations Rehabilitation
Project code
PRJ-2026-004
Project sponsor
Salma Al-ZaimSalma Al-ZaimDeputy President, Finance, Administration & the Investment PlanP-012salma.alzaim@psa.gov.sy
Project manager
Eng. Maher Al-HamawiEng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsP-021maher.alhamawi@psa.gov.sy
Project owner
Eng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.sy
Portfolio & programme
Energy & Water PortfolioEnergy & Water Systems Rehabilitation Programme
Type & methodology
Infrastructure · Construction
Current phase
4Execution

2Background & rationale

Required at this stage

⁦Rehabilitating four 230 kV substations in Aleppo city⁩ (⁦28 high-voltage bays⁩) and linking them to the control centre, to lengthen supply hours in the neighbourhoods and the industrial zone.

3Objectives

Required at this stage
  1. 1Rehabilitate core energy, water and transport infrastructure
  2. 2Stimulate growth, restore production and attract investment

4Scope

Required at this stage

In scope

  • ⁦Rehabilitating four 230 kV substations in Aleppo city⁩ (⁦28 high-voltage bays⁩) and linking them to the control centre, to lengthen supply hours in the neighbourhoods and the industrial zone.
  • Syrian Arab Building Code compliance
  • An approved plan to keep services running for residents during the works

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

5High-level requirements

Required at this stage
  1. 1Syrian Arab Building Code compliance
  2. 2An approved plan to keep services running for residents during the works
  3. 3Civil-defence requirements

6Deliverables

Required at this stage
1Project management plan⁦2024-02-23⁩
2Main deliverable — stage 1⁦2025-06-02⁩
3Main deliverable — final stage⁦2026-05-14⁩
4Final report⁦2026-09-30⁩

7Key milestones

Required at this stage
  1. Charter approved⁦2024-01-12⁩
  2. Contract signed⁦2024-06-20⁩
  3. 50% of works complete⁦2025-06-02⁩
  4. Provisional acceptance⁦2026-07-13⁩
  5. Closure⁦2026-09-30⁩

8Budget

Required at this stage
  • Main contract⁦72.0%⁩SYP7.4B
  • Supervision & consulting⁦14.0%⁩SYP1.4B
  • Internal team⁦9.0%⁩SYP927.5M
  • Contingency reserve (⁦5%⁩)⁦5.0%⁩SYP515M
The delivering body’s investment-plan allocationsTotalSYP10.3B

9Timeline

Required at this stage
Start
2024-01-1414 January 2024
Baseline finish
2026-09-3030 September 2026
Duration
⁦33⁩ months

10Key risks

Required at this stage
  • HighMain contractor cash-flow trouble and late payment of subcontractors
  • HighControl-room fire systems not meeting civil-defence requirements
  • MediumFaults in the new transformers during commissioning

11Constraints

Required at this stage
  • Stay within the approved budget
  • Comply with the unified contracts law (⁦Law 51 of 2004⁩)

12Assumptions

Required at this stage
  • Named internal staff available throughout
  • Approvals land within the workflow’s action time limits

13Stakeholders

Required at this stage
  • Project sponsorDecisions and funding
  • Project ownerAccepts deliverables, owns benefits
  • National Project Management Office (PMO)Governance and compliance

14Success criteria

Required at this stage
  1. 1Delivered within the approved budget
  2. 2On the approved date ⁦±5%⁩
  3. 3⁦Target benefits within 12 months⁩

15Governance structure

Required at this stage
  • Change CommitteeApproves scope, cost and schedule changesWeekly
  • Project Approval CommitteeMethodology compliance, data quality, stage gatesFortnightly
  • Project management teamDay-to-day control, risks, impediments, the periodic update cardWeekly