Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية

RSK-0022Aleppo 230 kV Substations Rehabilitation

Control-room fire systems not meeting civil-defence requirements

15HighOpenMaterial

A risk's detail, response, contingency and residual risk.

Risk statement

From cause to event to impact — with the preventive controls before the event and the contingency after it

Cause

Control-room drawings revised for the new bays were never shown to the Syrian Civil Defence, and fire rules are stricter for transformer rooms

Preventive controls

  • An early review of the fire and evacuation drawings with the Syrian Civil Defence
  • An integrated test of the alarm and fire systems before the official inspection

2 / 2

Event

Control-room fire systems not meeting civil-defence requirements

15HighTrigger

Major findings at the Civil Defence inspection

Contingency

Energise the rehabilitated existing bays first and hold the new ones until approved

Impact

No safety certificate, so the substations cannot be energised

SYP 300M

Assessment

The level before and after the response

Inherent

5
4
3
2
1
1
2
3
4
5
15High

Residual

5
4
3
2
1
1
2
3
4
5
8Medium

Exposure

SYP 300M

Residual

⁦47⁩% off the score

Score trend

Last six months

  • Score
  • Target residual

Escalation path

Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the PMO director

Last reviewed 9 days ago

  1. Project manager

    Current level

    Eng. Maher Al-Hamawi

    Currently followed up here
  2. 2

    Programme manager

    Eng. Rami Youssef

    Automatically at 15 days unreviewed · in 6 days
  3. 3

    PMO director

    Dr. Reem Al-Qabbani

    Automatically at 20 days unreviewed · in 11 days
  4. 4

    Executive Council

    Dr. Samer Al-Daqqar

    By the PMO director’s decision

Mitigation plan

Each action with its owner and date — tick it off when complete

⁦0⁩ of ⁦2⁩ done
  • An early review of the fire and evacuation drawings with the Syrian Civil Defence

    Eng. Rami YoussefEng. Rami YoussefDirector, Renewable Energy & Environment ProjectsP-028rami.youssef@psa.gov.sy
    In progressIn 18 days2026-11-15
  • An integrated test of the alarm and fire systems before the official inspection

    Eng. Maher Al-HamawiEng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsP-021maher.alhamawi@psa.gov.sy
    Not startedIn 53 days2026-12-20

Trigger

Major findings at the Civil Defence inspection

Contingency

Energise the rehabilitated existing bays first and hold the new ones until approved

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close