RSK-0022Aleppo 230 kV Substations Rehabilitation
Control-room fire systems not meeting civil-defence requirements
A risk's detail, response, contingency and residual risk.
Risk statement
From cause to event to impact — with the preventive controls before the event and the contingency after it
Cause
Control-room drawings revised for the new bays were never shown to the Syrian Civil Defence, and fire rules are stricter for transformer rooms
Preventive controls
- An early review of the fire and evacuation drawings with the Syrian Civil Defence
- An integrated test of the alarm and fire systems before the official inspection
2 / 2
Event
Control-room fire systems not meeting civil-defence requirements
Major findings at the Civil Defence inspection
Contingency
Energise the rehabilitated existing bays first and hold the new ones until approved
Impact
No safety certificate, so the substations cannot be energised
Assessment
The level before and after the response
Inherent
Residual
Exposure
SYP 300M
Residual
47% off the score
Score trend
Last six months
- Score
- Target residual
Escalation path
Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the PMO director
Last reviewed 9 days ago
Project manager
Current levelEng. Maher Al-Hamawi
Currently followed up here- 2
Programme manager
Eng. Rami Youssef
Automatically at 15 days unreviewed · in 6 days - 3
PMO director
Dr. Reem Al-Qabbani
Automatically at 20 days unreviewed · in 11 days - 4
Executive Council
Dr. Samer Al-Daqqar
By the PMO director’s decision
Mitigation plan
Each action with its owner and date — tick it off when complete
An early review of the fire and evacuation drawings with the Syrian Civil Defence
Eng. Rami YoussefEng. Rami YoussefDirector, Renewable Energy & Environment ProjectsP-028rami.youssef@psa.gov.syIn progressIn 18 days2026-11-15An integrated test of the alarm and fire systems before the official inspection
Eng. Maher Al-HamawiEng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsP-021maher.alhamawi@psa.gov.syNot startedIn 53 days2026-12-20
Trigger
Major findings at the Civil Defence inspection
Contingency
Energise the rehabilitated existing bays first and hold the new ones until approved