PRJ-2026-004
Aleppo 230 kV Substations RehabilitationPlanned to date 92%
- SPI
- 0.74
- Forecast finish
- 2027-02-03
- Budget
- SYP 10.3B
126 days lateMaterial risks: 2Open impediments: 3Corrective plan CP-2026-02
On-site handling of the Aleppo substations contractor’s distress.
Held on
27 October 202612:00 – 13:40
70 of 90 min
Overdue subcontractor payments
DiscussionOmar Al-Nahhas
40 min
Substation 2 transformer test results
DiscussionEng. Maher Al-Hamawi
30 min
Saved as you type
1. Overdue subcontractor payments
CTR-2024-0032. Substation 2 transformer test results
ISS-0114No decisions recorded
Record the decision and put it to a vote if needed.
They show in the task register and on the owner’s calendar
ACT-0308Rasha Al-Mudarres
Project meeting — no quorum required
1 file
Drafted by the assistant from the agenda, the minutes, the decisions and the tasks. Review it before approval.
Shown only to invitees and the PMO, and leaves out what your permissions do not let you see.
Built automatically from the projects on the agenda: a card per project, the decisions needed, the support requested and the overdue tasks.
PRJ-2026-004
Aleppo 230 kV Substations RehabilitationPlanned to date 92%
126 days lateMaterial risks: 2Open impediments: 3Corrective plan CP-2026-02
Nothing
ISS-0113 · Aleppo 230 kV Substations Rehabilitation
FundingSYP 160M· Asked from: Authority Executive Council
Approve paying four subcontractors directly from certificate 34, deducted from the main contractor
ACT-0307 · Omar Al-Nahhas