RSK-0021Aleppo 230 kV Substations Rehabilitation

Main contractor cash-flow trouble and late payment of subcontractors

25CriticalEscalatedMaterial

A risk's detail, response, contingency and residual risk.

Risk statement

From cause to event to impact — with the preventive controls before the event and the contingency after it

Cause

Late payment of earlier certificates and weak finances at the main contractor

Preventive controls

  • An executive task force on the contractor’s distress
  • Pay critical subcontractors directly with the contractor’s consent
  • Fast-track certificate 33

2 / 3

Event

Main contractor cash-flow trouble and late payment of subcontractors

25CriticalTrigger

Site work stopped for more than 7 consecutive days

Contingency

Take part of the works away and give it to a second contractor under the contract

Impact

Subcontractors and labour idle, substation commissioning more than four months late, and rationing continuing in eastern Aleppo

SYP 900M

Assessment

The level before and after the response

Inherent

5
4
3
2
1
1
2
3
4
5
25Critical

Residual

5
4
3
2
1
1
2
3
4
5
12Medium

Exposure

SYP 900M

Residual

⁦52⁩% off the score

Score trend

Last six months

  • Score
  • Target residual

Escalation path

Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the PMO director

Last reviewed 1 day ago

  1. Project manager

    Eng. Maher Al-Hamawi

    Currently followed up here
  2. Programme manager

    Current level

    Eng. Rami Youssef

    Automatically at 15 days unreviewed · in 14 days
  3. 3

    PMO director

    Dr. Reem Al-Qabbani

    Automatically at 20 days unreviewed · in 19 days
  4. 4

    Executive Council

    Dr. Samer Al-Daqqar

    By the PMO director’s decision

Mitigation plan

Each action with its owner and date — tick it off when complete

⁦1⁩ of ⁦3⁩ done
  • An executive task force on the contractor’s distress

    Eng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.sy
    Done2026-09-222026-09-22
  • Pay critical subcontractors directly with the contractor’s consent

    Omar Al-NahhasOmar Al-NahhasSenior Finance & Contracts SpecialistP-007omar.alnahhas@psa.gov.sy
    In progressIn 8 days2026-11-05
  • Fast-track certificate 33

    Omar Al-NahhasOmar Al-NahhasSenior Finance & Contracts SpecialistP-007omar.alnahhas@psa.gov.sy
    Overdue3 days overdue2026-10-25

Trigger

Site work stopped for more than 7 consecutive days

Contingency

Take part of the works away and give it to a second contractor under the contract

Esc