Financial audit of the contractor — Aleppo substations
Aleppo 230 kV Substations Rehabilitation
1. Executive summary
This report gives the position of Aleppo 230 kV Substations Rehabilitation to date: 68% complete against 92% planned, SPI 0.74, CPI 0.84, and an estimate at completion of SYP 12.26bn.
- Project
- Aleppo 230 kV Substations Rehabilitation (PRJ-2026-004)
- Project manager
- Eng. Maher Al-Hamawi
- Budget
- SYP 10.30bn
- Progress
- 68% actual against 92% planned
- Forecast finish
- 2027-02-03
2. Key findings
- All planned milestones of the period met except one deferred
- Actual spend rose in line with the work done
- Three high risks under treatment, each with a named owner
3. Recommendations & decisions needed
- Approve the proposed treatment of the high risks
- Track the open findings with the vendor weekly
Prepared by
Omar Al-Nahhas
Project manager
Eng. Maher Al-Hamawi