Syrian Arab Republic
Planning and Statistics Authority
Incoming & Outgoing Mail
- Number:
- ص/2026/0406
- Date:
- 19 October 2026
- Attachments:
- 0
CONFIDENTIAL
Subject: Default notice and request for a corrective plan
Al-Shahbaa Construction & Rehabilitation Co.
Greetings,
With reference to contract PSA/2024/003, progress has fallen to 68% against 92% planned and the supply of transformers and high-voltage bays for the eastern substation has stopped. This letter is formal notice of default under the contract and the contracts law.
Submit a corrective plan approved by your management within fourteen days, failing which the Authority will act as the contract allows, including withdrawing the work and completing it at your cost.
With our kind regards,
President, Planning and Statistics Authority
Dr. Samer Al-Daqqar
Copy to:
- Al-Assi Project Management Group (supervising consultant)
- Legal Affairs