PRJ-2026-004Critical4ExecutionConstructionStalledDelivered by:Ministry of Energy

Aleppo 230 kV Substations Rehabilitation

Remove from watchlist

Rehabilitating four 230 kV substations in Aleppo city (28 high-voltage bays) and linking them to the control centre, to lengthen supply hours in the neighbourhoods and the industrial zone.

Early warning: ⁦95%⁩ chance of slipping within ⁦30⁩ days

Budget (BAC)

SYP 10.3B

Actual cost

SYP 8.3B

⁦81%⁩ of budget

Progress

⁦68%⁩Awaiting acceptance ⁦9%⁩

Estimate at completion

SYP 12.3B

+SYP 2B

SPI · CPI

0.74Schedule performance index · 0.740.84Cost performance index · 0.84

Forecast finish

⁦2027-02-03⁩

126 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure13 July 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate15 November 2023Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate14 January 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate20 June 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate13 July 2026Closure · Not startedClosure · Not started

Corrective plan

Actions, owners, dates and status

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Corrective plan

Actions, owners, dates and status

Form no.
PSA-PMO-F11
Template edition
1.4
Version
V1
Form date
⁦2026-09-17⁩
ApprovedCP-2026-02Corrective plan — Aleppo 230 kV Substations Rehabilitation

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-004
Project
Aleppo 230 kV Substations Rehabilitation
Portfolio
Energy & Water Portfolio
Sector
Development Projects Follow-up Sector
Sponsor
Salma Al-Zaim
Project manager
Eng. Maher Al-Hamawi

1Why the planAuto-filled

Slip when detected

104 days

SPI

0.76

Finish without the plan

⁦2027-03-20⁩

Finish with the plan

⁦2027-02-03⁩

Causes

The main contractor’s cash-flow distress and unpaid subcontractors, an oil leak in substation 2’s transformer during testing, and control-room changes never shown to Civil Defence

2Actions

ActionOwnerDueStatusDays won back
An executive task force on the contractor’s distressEng. Wassim Al-Azm⁦2026-09-22⁩Done0
Appoint an independent financial adviser to audit contractor liquidityOmar Al-Nahhas⁦2026-10-20⁩In progress10
Pay subcontractors directly from the next certificateOmar Al-Nahhas⁦2026-11-05⁩Not started20
Re-test the transformer after replacing the gasketsEng. Maher Al-Hamawi⁦2026-11-02⁩In progress5
An early review of the fire and evacuation drawings with the Syrian Civil DefenceEng. Rami Youssef⁦2026-11-15⁩In progress10
Total———45

3Support requested

Amount
SYP 160M
Detail
Pay four subcontractors directly from certificate 34

4PMO follow-upAuto-filled

DateSPISlipNote
⁦2026-10-27⁩0.74126Labour stopped for four days; direct payment raised to the Executive Council (ESC-2026-021)
⁦2026-10-13⁩0.75118The financial adviser is still not appointed (conflict of interest); re-tendering

Approval logChain: Corrective plan approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsSubmitted—⁦2026-09-17⁩ 11:56
2Programme manager reviewTechnical acceptanceEng. Abdulrahman Al-KilaniProgramme managerApproved—⁦2026-09-21⁩ 13:28
3Financial support requestedFinancial approvalRasha Al-MudarresFinanceApproved—⁦2026-09-22⁩ 13:22
4National Projects Steering Committee approvalTechnical acceptanceDr. Samer Al-DaqqarNational Projects Steering CommitteeApproved—⁦2026-09-24⁩ 09:42

Signatures

Programme manager review

Eng. Abdulrahman Al-Kilani

Approved⁦2026-09-21⁩

Financial support requested

Rasha Al-Mudarres

Approved⁦2026-09-22⁩

National Projects Steering Committee approval

Dr. Samer Al-Daqqar

Approved⁦2026-09-24⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F11 · version V1

Corrective plan

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Corrective plan approval · version ⁦1⁩

Submitted by Eng. Maher Al-Hamawi on ⁦2026-09-17⁩

  1. Technical acceptance

    Programme manager review

    Eng. Abdulrahman Al-Kilani · Programme manager

    Approved · ⁦2026-09-21⁩ at ⁦13:28⁩

  2. Financial approval

    Financial support requested

    Rasha Al-Mudarres · Finance

    On the path because: Financial link?

    Approved · ⁦2026-09-22⁩ at ⁦13:22⁩

  3. Technical acceptance

    National Projects Steering Committee approval

    Dr. Samer Al-Daqqar · National Projects Steering Committee

    Approved · ⁦2026-09-24⁩ at ⁦09:42⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V1ApprovedCurrent⁦2026-09-17⁩

    The current version

    Eng. Maher Al-Hamawi

Only one version so far.