PRJ-2026-010On track4ExecutionConstructionIn progressDelivered by:Ministry of Energy

20 MW Qalamoun Solar Field

Add to watchlist

A 20 MW photovoltaic field near An-Nabk feeding the public grid, with a substation and a 66 kV connection line.

Budget (BAC)

SYP 2.4B

Actual cost

SYP 1.4B

⁦57%⁩ of budget

Progress

⁦58%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SYP 2.4B

SPI · CPI

1.02Schedule performance index · 1.021.01Cost performance index · 1.01

Forecast finish

⁦2027-04-22⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure26 February 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate1 January 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate2 March 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate6 July 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate26 February 2027Closure · Not startedClosure · Not started

Scope statementRequired at this stage

What the project delivers, what it does not, and when a deliverable counts as accepted.

A ⁦20 MW photovoltaic field near An-Nabk feeding the public grid⁩, ⁦with a substation and a 66 kV connection line⁩.

In scope

  • A ⁦20 MW photovoltaic field near An-Nabk feeding the public grid⁩, ⁦with a substation and a 66 kV connection line⁩.
  • Syrian Arab Building Code compliance
  • An approved plan to keep services running for residents during the works

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

Acceptance criteria

  • Main deliverable — stage 1Meets the approved specification, signed off by the project owner
  • Main deliverable — final stageMeets the approved specification, signed off by the project owner

Scope baselineRequired at this stage

Every approved change creates a new baseline

  1. 1

    SB-1Current⁦2025-04-09⁩

    Baseline approved at the planning gate

    BudgetSYP2.4BFinish⁦2027-04-30⁩

Requirements registerRequired at this stage

⁦6⁩ requirements of five kinds, with the trace status of each

By type

  • Business1
  • Functional1
  • Technical1
  • Regulatory2
  • Security1

Fully traced

⁦100%⁩

6/6 · linked to a deliverable, task and test

Test passed

⁦33%⁩

2/6 · test result is a pass

Accepted

⁦33%⁩

2/6 · signed off by the business owner

⁦6⁩ results
Export CSV
REQ-010-01Reach the target capacity of rehabilitated facilitiesBusinessMustIn progressEng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.sySB-1
REQ-010-02Meet the approved technical specsTechnicalMustApprovedEng. Rami YoussefEng. Rami YoussefDirector, Renewable Energy & Environment ProjectsP-028rami.youssef@psa.gov.sySB-1
REQ-010-03Services to residents continue during the worksFunctionalMustIn progressEng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.sySB-1
REQ-010-04Syrian Arab Building CodeRegulatoryShouldIn progressEng. Rami YoussefEng. Rami YoussefDirector, Renewable Energy & Environment ProjectsP-028rami.youssef@psa.gov.sySB-1
REQ-010-05Civil-defence requirementsRegulatoryShouldIn progressEng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.sySB-1
REQ-010-06Site and systems securitySecurityCouldApprovedEng. Rami YoussefEng. Rami YoussefDirector, Renewable Energy & Environment ProjectsP-028rami.youssef@psa.gov.sySB-1
⁦1⁩–⁦6⁩ of ⁦6⁩

Traceability matrixRequired at this stage

Requirement → deliverable → task → test → acceptance. No requirement has a gap.