PRJ-2026-010On track4ExecutionConstructionIn progressDelivered by:Ministry of Energy

20 MW Qalamoun Solar Field

Add to watchlist

A 20 MW photovoltaic field near An-Nabk feeding the public grid, with a substation and a 66 kV connection line.

Budget (BAC)

SYP 2.4B

Actual cost

SYP 1.4B

⁦57%⁩ of budget

Progress

⁦58%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SYP 2.4B

SPI · CPI

1.02Schedule performance index · 1.021.01Cost performance index · 1.01

Forecast finish

⁦2027-04-22⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure26 February 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate1 January 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate2 March 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate6 July 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate26 February 2027Closure · Not startedClosure · Not started
Fields required by the project’s stage (Execution): 15 fields required now.Field settings

Planning and Statistics Authority

Project charter

20 MW Qalamoun Solar Field

APPROVEDV2Approved ⁦2025-02-28⁩

1Project identity

Required at this stage
Project name
20 MW Qalamoun Solar Field
Project code
PRJ-2026-010
Project sponsor
Salma Al-ZaimSalma Al-ZaimDeputy President, Finance, Administration & the Investment PlanP-012salma.alzaim@psa.gov.sy
Project manager
Eng. Rami YoussefEng. Rami YoussefDirector, Renewable Energy & Environment ProjectsP-028rami.youssef@psa.gov.sy
Project owner
Eng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.sy
Portfolio & programme
Energy & Water PortfolioEnergy & Water Systems Rehabilitation Programme
Type & methodology
Infrastructure · Construction
Current phase
4Execution

2Background & rationale

Required at this stage

A ⁦20 MW photovoltaic field near An-Nabk feeding the public grid⁩, ⁦with a substation and a 66 kV connection line⁩.

3Objectives

Required at this stage
  1. 1Rehabilitate core energy, water and transport infrastructure
  2. 2Stimulate growth, restore production and attract investment

4Scope

Required at this stage

In scope

  • A ⁦20 MW photovoltaic field near An-Nabk feeding the public grid⁩, ⁦with a substation and a 66 kV connection line⁩.
  • Syrian Arab Building Code compliance
  • An approved plan to keep services running for residents during the works

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

5High-level requirements

Required at this stage
  1. 1Syrian Arab Building Code compliance
  2. 2An approved plan to keep services running for residents during the works
  3. 3Civil-defence requirements

6Deliverables

Required at this stage
1Project management plan⁦2025-04-02⁩
2Main deliverable — stage 1⁦2026-04-09⁩
3Main deliverable — final stage⁦2027-01-10⁩
4Final report⁦2027-04-30⁩

7Key milestones

Required at this stage
  1. Charter approved⁦2025-02-28⁩
  2. Contract signed⁦2025-07-06⁩
  3. 50% of works complete⁦2026-04-09⁩
  4. Provisional acceptance⁦2027-02-26⁩
  5. Closure⁦2027-04-30⁩

8Budget

Required at this stage
  • Main contract⁦72.0%⁩SYP1.7B
  • Supervision & consulting⁦14.1%⁩SYP337.5M
  • Internal team⁦9.0%⁩SYP215M
  • Contingency reserve (⁦5%⁩)⁦5.0%⁩SYP120M
The delivering body’s investment-plan allocationsTotalSYP2.4B

9Timeline

Required at this stage
Start
2025-03-022 March 2025
Baseline finish
2027-04-3030 April 2027
Duration
⁦26⁩ months

10Key risks

Required at this stage
  • MediumLower world PV prices allow a larger field within the allocation

11Constraints

Required at this stage
  • Stay within the approved budget
  • Comply with the unified contracts law (⁦Law 51 of 2004⁩)

12Assumptions

Required at this stage
  • Named internal staff available throughout
  • Approvals land within the workflow’s action time limits

13Stakeholders

Required at this stage
  • Project sponsorDecisions and funding
  • Project ownerAccepts deliverables, owns benefits
  • National Project Management Office (PMO)Governance and compliance

14Success criteria

Required at this stage
  1. 1Delivered within the approved budget
  2. 2On the approved date ⁦±5%⁩
  3. 3⁦Target benefits within 12 months⁩

15Governance structure

Required at this stage
  • Change CommitteeApproves scope, cost and schedule changesWeekly
  • Project Approval CommitteeMethodology compliance, data quality, stage gatesFortnightly
  • Project management teamDay-to-day control, risks, impediments, the periodic update cardWeekly
Version V2 · ⁦4⁩ of ⁦4⁩ signaturesInternal — not for circulation outside the Authority