PRJ-2026-010On track4ExecutionConstructionIn progressDelivered by:Ministry of Energy

20 MW Qalamoun Solar Field

Add to watchlist

A 20 MW photovoltaic field near An-Nabk feeding the public grid, with a substation and a 66 kV connection line.

Budget (BAC)

SYP 2.4B

Actual cost

SYP 1.4B

⁦57%⁩ of budget

Progress

⁦58%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SYP 2.4B

SPI · CPI

1.02Schedule performance index · 1.021.01Cost performance index · 1.01

Forecast finish

⁦2027-04-22⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure26 February 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate1 January 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate2 March 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate6 July 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate26 February 2027Closure · Not startedClosure · Not started

Project charter

Objective, scope, deliverables, roles and budget

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Initiation

Project charter

Objective, scope, deliverables, roles and budget

Form no.
PSA-PMO-F04
Template edition
3.0
Version
V2
Form date
⁦2025-02-28⁩
ApprovedPRJ-2026-01020 MW Qalamoun Solar Field

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-010
Project
20 MW Qalamoun Solar Field
Portfolio
Energy & Water Portfolio
Sector
Development Projects Follow-up Sector
Sponsor
Salma Al-Zaim
Project manager
Eng. Rami Youssef

1Objective

Background

A 20 MW photovoltaic field near An-Nabk feeding the public grid, with a substation and a 66 kV connection line.

Project objectives

  1. Rehabilitate core energy, water and transport infrastructure
  2. Stimulate growth, restore production and attract investment

2Scope

In scope

  • A 20 MW photovoltaic field near An-Nabk feeding the public grid, with a substation and a 66 kV connection line.
  • Syrian Arab Building Code compliance
  • An approved plan to keep services running for residents during the works

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

3Deliverables and milestones

DeliverableDue
Project management plan⁦2025-04-02⁩
Main deliverable — stage 1⁦2026-04-09⁩
Main deliverable — final stage⁦2027-01-10⁩
Final report⁦2027-04-30⁩
MilestoneDate
Charter approved⁦2025-02-28⁩
Contract signed⁦2025-07-06⁩
50% of works complete⁦2026-04-09⁩
Provisional acceptance⁦2027-02-26⁩
Closure⁦2027-04-30⁩

4RolesAuto-filled

SponsorAuto-filled
Salma Al-Zaim
Project ownerAuto-filled
Eng. Wassim Al-Azm
Project managerAuto-filled
Eng. Rami Youssef
StakeholderRole
Project sponsorDecisions and funding
Project ownerAccepts deliverables, owns benefits
National Project Management Office (PMO)Governance and compliance
Governance bodyRoleCadence
Change CommitteeApproves scope, cost and schedule changesWeekly
Project Approval CommitteeMethodology compliance, data quality, stage gatesFortnightly
Project management teamDay-to-day control, risks, impediments, the periodic update cardWeekly

5BudgetAuto-filled

LineAmount
Main contractSYP 1.7B
Supervision & consultingSYP 337.5M
Internal teamSYP 215M
Contingency reserve (5%)SYP 120M
Approved budgetSYP 2.4B

Funding

The delivering body’s investment-plan allocations

6Success criteria and constraints

Success criteria

  • Delivered within the approved budget
  • On the approved date ±5%
  • Target benefits within 12 months

Constraints

  • Stay within the approved budget
  • Comply with the unified contracts law (Law 51 of 2004)

Assumptions

  • Named internal staff available throughout
  • Approvals land within the workflow’s action time limits

Approval logChain: Project charter approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Rami YoussefDirector, Renewable Energy & Environment ProjectsSubmitted—⁦2025-02-19⁩ 10:00
2PMO complianceMethodology reviewDr. Reem Al-QabbaniPMO — directorApproved—⁦2025-02-22⁩ 12:30
3Project ownerTechnical acceptanceEng. Wassim Al-AzmProject ownerApproved—⁦2025-02-25⁩ 09:45
4Budget funding confirmedFinancial approvalRasha Al-MudarresFinanceApproved—⁦2025-02-26⁩ 11:10
5Sponsor approvalTechnical acceptanceSalma Al-ZaimProject sponsorApproved—⁦2025-02-28⁩ 11:00

Signatures

PMO compliance

Dr. Reem Al-Qabbani

Approved⁦2025-02-22⁩

Project owner

Eng. Wassim Al-Azm

Approved⁦2025-02-25⁩

Budget funding confirmed

Rasha Al-Mudarres

Approved⁦2025-02-26⁩

Sponsor approval

Salma Al-Zaim

Approved⁦2025-02-28⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F04 · version V2

Project charter

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project charter approval · version ⁦1⁩

Submitted by Eng. Rami Youssef on ⁦2025-02-19⁩

  1. Methodology review

    PMO compliance

    Dr. Reem Al-Qabbani · PMO — director

    Approved · ⁦2025-02-22⁩ at ⁦12:30⁩

  2. Technical acceptance

    Project owner

    Eng. Wassim Al-Azm · Project owner

    Approved · ⁦2025-02-25⁩ at ⁦09:45⁩

  3. Financial approval

    Budget funding confirmed

    Rasha Al-Mudarres · Finance

    On the path because: Financial link?

    Approved · ⁦2025-02-26⁩ at ⁦11:10⁩

  4. Technical acceptance

    Sponsor approval

    Salma Al-Zaim · Project sponsor

    Approved · ⁦2025-02-28⁩ at ⁦11:00⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2025-02-28⁩

    Approved version

    • PMO comments addressed

    Eng. Rami Youssef

  2. V1Returned for edit⁦2025-02-09⁩

    First draft

    • Returned to detail the budget

    Eng. Rami Youssef