PRJ-2026-010On track4ExecutionConstructionIn progressDelivered by:Ministry of Energy

20 MW Qalamoun Solar Field

Add to watchlist

A 20 MW photovoltaic field near An-Nabk feeding the public grid, with a substation and a 66 kV connection line.

Budget (BAC)

SYP 2.4B

Actual cost

SYP 1.4B

⁦57%⁩ of budget

Progress

⁦58%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SYP 2.4B

SPI · CPI

1.02Schedule performance index · 1.021.01Cost performance index · 1.01

Forecast finish

⁦2027-04-22⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure26 February 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate1 January 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate2 March 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate6 July 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate26 February 2027Closure · Not startedClosure · Not started

Team & roles

2 members, about ⁦0.6⁩ full-time equivalents

Leadership

2 members

  • Eng. Rami YoussefProject manager⁦45%⁩Allocated ⁦105%⁩ across all projectsA
  • Eng. Wassim Al-AzmProject owner⁦15%⁩Allocated ⁦105%⁩ across all projectsR

A AccountableR ResponsibleC ConsultedI Informed

Stakeholders

⁦6⁩ stakeholders, ⁦4⁩ of them below the engagement needed

Power / interest matrix

Pick one to see how they are handled

Power & influence

Keep satisfied1

high power, lower interest

Manage closely4

high power and interest

Monitor0

minimal effort

Keep informed1

high interest, lower power

Salma Al-ZaimManage closelyEng. Wassim Al-AzmManage closelyProject Management Office (PMO)Manage closelyEnd beneficiariesKeep informedGeneral Directorate of Financial AffairsKeep satisfiedAlternative Energy Contracting Est.Manage closely

Interest

Project sponsor

Salma Al-Zaim

Decisions and funding

Influence

Interest

Engagement level

Unaware

Resistant

Neutral

Now

Supportive

Target

Leading

A gap of ⁦1⁩ step — needs an engagement plan.

Impact on the project
Approves gates and changes
Engagement plan
Monthly briefing
Last contact⁦2026-10-20⁩
⁦6⁩ results
Export CSV
OrganisationRoleActions
Salma Al-ZaimProject sponsorDecisions and fundingSupportiveLeadingEng. Rami YoussefEng. Rami YoussefDirector, Renewable Energy & Environment ProjectsP-028rami.youssef@psa.gov.sy⁦2026-10-20⁩
Eng. Wassim Al-AzmProject ownerAccepts deliverables, owns benefitsNeutralLeadingEng. Rami YoussefEng. Rami YoussefDirector, Renewable Energy & Environment ProjectsP-028rami.youssef@psa.gov.sy⁦2026-10-23⁩
Project Management Office (PMO)GovernanceCompliance and data qualitySupportiveEng. Rami YoussefEng. Rami YoussefDirector, Renewable Energy & Environment ProjectsP-028rami.youssef@psa.gov.sy⁦2026-10-17⁩
General Directorate of Financial AffairsInternal departmentPayment approvalNeutralSupportiveHuda Al-DandalHuda Al-DandalSenior Financial Analyst — Investment PlanP-037huda.aldandal@psa.gov.sy⁦2026-10-14⁩
Alternative Energy Contracting Est.Main vendorDelivers the contracted workSupportiveEng. Rami YoussefEng. Rami YoussefDirector, Renewable Energy & Environment ProjectsP-028rami.youssef@psa.gov.sy⁦2026-10-24⁩
End beneficiariesBeneficiariesUsers of the outcomeNeutralSupportiveEng. Rami YoussefEng. Rami YoussefDirector, Renewable Energy & Environment ProjectsP-028rami.youssef@psa.gov.sy⁦2026-09-26⁩
⁦1⁩–⁦6⁩ of ⁦6⁩

Communication plan

Who needs what, when, through which channel, and who owns it.

  • Project sponsorStatus and decisions neededMonthlyMeetingEng. Rami Youssef⁦2026-11-15⁩
  • Project ownerDeliverable status and acceptance datesFortnightlyEmailEng. Rami Youssef⁦2026-11-03⁩
  • PMOData and indicator updatesWeeklyDashboardEng. Rami Youssef⁦2026-10-31⁩
  • BeneficiariesWhat changes and whenAt milestonesNewsletterEng. Rami YoussefAt launch

Coming up

By date

  1. 312026-10PMODashboard · Weekly
  2. 032026-11Project ownerEmail · Fortnightly
  3. 152026-11Project sponsorMeeting · Monthly