Original
Original baseline
- Finish
- 2027-04-30
- Budget
- SYP 2.4B
- 17 activities
Approved with the project plan at the planning gate.
Approved 2025-03-02 · by Salma Al-Zaim
A 20 MW photovoltaic field near An-Nabk feeding the public grid, with a substation and a 66 kV connection line.
Budget (BAC)
Actual cost
57% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
On baseline
ExecutionStage 4 of 5
Next gate:Closure26 February 2027
The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.
Original
Approved with the project plan at the planning gate.
Approved 2025-03-02 · by Salma Al-Zaim
Working
Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.
Created 2026-10-28 · by Eng. Rami Youssef
What changed from version A to version B
Finish
2027-04-302027-04-30
0 days
Budget
SYP 2.4BSYP 2.4B
0.00 SYP M
Milestones moved
4 / 5
Each line starts at the milestone’s date in A and ends at its date in B
Version AVersion B
Difference in SYP millions from A to B
Every saved version with its reason and reference