PRJ-2026-010On track4ExecutionConstructionIn progressDelivered by:Ministry of Energy

20 MW Qalamoun Solar Field

Add to watchlist

A 20 MW photovoltaic field near An-Nabk feeding the public grid, with a substation and a 66 kV connection line.

Budget (BAC)

SYP 2.4B

Actual cost

SYP 1.4B

⁦57%⁩ of budget

Progress

⁦58%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SYP 2.4B

SPI · CPI

1.02Schedule performance index · 1.021.01Cost performance index · 1.01

Forecast finish

⁦2027-04-22⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure26 February 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate1 January 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate2 March 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate6 July 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate26 February 2027Closure · Not startedClosure · Not started

Baselines

The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.

  1. Original

    Original baseline

    v1.0Approved & lockedVersion A
    Finish
    ⁦2027-04-30⁩
    Budget
    SYP 2.4B
    ⁦17⁩ activities

    Approved with the project plan at the planning gate.

    Approved ⁦2025-03-02⁩ · by Salma Al-Zaim

  2. Working

    Working baseline

    v2.0-draftWorking draftVersion B
    Finish
    ⁦2027-04-30⁩
    Budget
    SYP 2.4B
    ⁦17⁩ activities

    Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.

    Created ⁦2026-10-28⁩ · by Eng. Rami Youssef

    Edit in the schedule

Compare two versions

What changed from version A to version B

Finish

⁦2027-04-30⁩⁦2027-04-30⁩

⁦0⁩ days

Budget

SYP 2.4BSYP 2.4B

⁦0.00⁩ SYP M

Milestones moved

4 / 5

Milestones: A to B

Each line starts at the milestone’s date in A and ends at its date in B

2026-012026-072027-01
  • Project plan approved⁦+44⁩
  • Designs approved⁦+78⁩
  • Build complete⁦+127⁩
  • Testing & acceptance complete⁦+69⁩
  • Final handover

Version AVersion B

Cost by WBS element

Difference in SYP millions from A to B

  • 1Management & governance⁦+2.89⁩
  • 2Design & permits⁦+5.79⁩
  • 3Civil works⁦+66.33⁩
  • 4MEP works⁦−9.85⁩
  • 5Handover⁦−4.93⁩

Version history

Every saved version with its reason and reference

  1. Working baselinev2.0-draftWorking draftFollows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.⁦2026-10-28⁩by Eng. Rami Youssef
  2. Original baselinev1.0Approved & lockedApproved with the project plan at the planning gate.⁦2025-03-02⁩by Salma Al-Zaim